  1. Why void work matters
  2. Heated or drained? Decide on day one
  3. The void inspection
  4. Frost protection that actually protects
  5. Drain-down procedure
  6. Stagnation and legionella
  7. Reinstatement before the new tenant
  8. Turning voids round faster
  9. Social housing voids and Awaab's Law
  10. Worked Example: a winter void
  11. Frequently asked questions
  12. References

Key takeaways

  • Decide early whether a void stays heated on frost protection or is drained down; the length of the void and the season decide it.
  • Winter is the risky period: UK household gas demand in early 2026 was more than five times the summer level[1], and empty homes freeze when nobody notices the heating has failed.
  • Stagnant water is a legionella risk: HSE says water should not stagnate, outlets should be used at least weekly and long vacancies may need flushing or draining[2].
  • Reinstatement is a full recommissioning job, ending with a gas safety record the tenant receives before moving in[3].
  • For social landlords in England, hazards found in a void fall under Awaab's Law timescales once a tenant is in, including 24 hours for emergency hazards[4].

Why void work matters

Every week a rented home stands empty costs the landlord rent, and every fault found after the new tenant moves in costs them goodwill. Void works are the jobs done between tenancies to make the home safe, working and ready to let: repairs, safety checks, frost protection while it is empty and reinstatement before the keys go to the next tenant. For a plumbing and heating firm, voids are a steady source of work from housing associations, councils, letting agents and portfolio landlords, provided you can turn them round quickly and reliably.

Speed matters, but so does sequence. Many voids go wrong not because the work is hard but because it is done in the wrong order: heating left off in a cold snap, systems drained without labels, or a gas check booked before the plumbing repairs are finished.

Heated or drained? Decide on day one

Example decision guide for empty rented homes.
SituationRecommended approachWhy
Short void, days to a few weeks, works on siteKeep heating on with frost protection; isolate unused outletsContractors need water and heat; reinstatement is quick
Short void in winter, no works plannedFrost protection on, with a weekly check visitA failed boiler in an empty house is how pipes burst
Long void, months, no worksDrain down hot, cold and heating systems; label everythingRemoves frost and stagnation risk; needs full reinstatement later
Refurbishment voidKeep a temporary water supply and drain sections as work progressesTrades need water; empty sections cannot freeze
Probate or uncertain lengthDrain down unless someone can check weeklyNobody may visit for long periods

Agree the approach in writing with the landlord or void manager on the first visit, record it on the job and leave a notice at the stopcock and boiler saying what state the system is in.

The void inspection

The first visit sets up everything else. Walk the whole property with the plumbing and heating in mind, photograph as you go and write a short schedule of works before anyone starts.

  1. Locate and test the stopcock, and note whether it can be turned off fully.
  2. Check every tap, valve, waste, trap and WC for leaks, drips and damage.
  3. Look under baths, showers, sinks and kitchen units for signs of past leaks and damp.
  4. Run the boiler or heat pump, check pressure, controls and every radiator, and note any that stay cold.
  5. Check the cylinder, its valves and discharge, and the cold water tank if there is one.
  6. Note missing or expired carbon monoxide and smoke alarms.
  7. Record meter readings and whether supplies are on.
  8. List what must be done before letting, what can wait and what needs the landlord’s approval.

Frost protection that actually protects

The risk is seasonal. UK household gas demand in the first quarter of 2026 was 109,126 GWh, against 19,636 GWh in the third quarter of 2025[1]. Demand on heating systems and the risk of freezing both peak in the same months, which is exactly when an empty house with a faulty boiler does the most damage.

UK household gas demand, summer against winterDomestic gas demand; Department for Energy Security and Net Zero
UK household gas demand, summer against winterComparison. July to September 2025: 19,636 GWh; January to March 2026: 109,126 GWh.19,636 GWhJuly to September 2025July to September 2025: 19,636 GWh109,126 GWhJanuary to March 2026January to March 2026: 109,126 GWhUK household gas demand, summer against winterComparison. July to September 2025: 19,636 GWh; January to March 2026: 109,126 GWh.19,636 GWhJuly to September 2025July to September 2025: 19,636 GWh109,126 GWhJanuary to March 2026January to March 2026: 109,126 GWh

Source: Department for Energy Security and Net Zero, 2026[1]

Show the data
ItemValue
July to September 202519,636 GWh
January to March 2026109,126 GWh
  • Keep gas and electricity supplies on, and make sure the meter has credit if it is prepaid.
  • Set the boiler or controls to frost protection, and check the frost thermostat actually brings the system on.
  • Lag exposed pipes in lofts, garages, under floors and on outside walls, and the cold water tank.
  • Isolate and drain outside taps.
  • Leave loft hatches closed and internal doors open so warmth reaches cold spots.
  • Arrange a weekly check, logged with the time, temperature and anything found.

A frost setting is only as good as the boiler behind it. If a void is heated through winter, someone must check it is still running.

Drain-down procedure

  1. Isolate

    Turn off the stopcock and, where possible, the supply at the boundary. Switch off the boiler and the immersion heater at the isolator.

  2. Drain the cold system

    Open the lowest cold taps and drain points. Drain the cold water storage tank if there is one.

  3. Drain the hot water

    With the immersion and boiler off, drain the cylinder through its drain cock. For unvented cylinders, follow the manufacturer's procedure for the safety devices.

  4. Drain the heating

    Drain the heating system from the lowest point, noting any inhibitor or antifreeze for reinstatement.

  5. Deal with traps and cisterns

    Empty WC cisterns and consider the risk of traps drying out and allowing drain smells; follow the landlord's specification.

  6. Label and record

    Tag the stopcock, boiler, cylinder and consumer unit: drained down, do not use. Record what was drained and the date.

Stagnation and legionella

Empty homes are where water stagnates. HSE says it is important that water is not allowed to stagnate within the system, that outlets should be used at least once a week, and that a flushing regime or draining may be needed for long vacancies[2]. HSE also lists flushing out the system before letting among the simple control measures[2].

For heated voids, a weekly visit that runs every outlet for a couple of minutes covers both the frost check and the stagnation risk. When the system is reinstated, set the cylinder to store at 60°C and check hot water reaches 50°C at the outlets within one minute[5].

Reinstatement before the new tenant

  1. Refill the cold system slowly, checking every joint, tap and appliance connection for leaks.
  2. Flush every outlet, hot and cold, until the water runs clear and fresh.
  3. Refill and vent the heating system, restore inhibitor to the right concentration and check the pressure.
  4. Recommission the boiler or heat pump, and check controls, programmer and thermostats.
  5. Refill WC cisterns and check traps hold water.
  6. Set the cylinder temperature and check outlet temperatures.
  7. Test carbon monoxide and smoke alarms and report any missing or faulty ones.
  8. Carry out the gas safety check and give the record to the landlord, who must give it to the tenant before they move in[3].

Book the gas safety check last, after any plumbing or heating repairs, so the record reflects the system the tenant will actually use.

Turning voids round faster

Void managers judge contractors on days lost. Most delays come from waiting: for keys, for approval, for parts, for another trade to finish. You can remove several of them.

  • Agree a standard void specification with each client so routine items do not need separate approval.
  • Carry the common void parts on the van: tap cartridges, fill valves, flush valves, traps, radiator valves and alarms.
  • Book the reinstatement and gas safety visit as soon as the works programme is known, not when the last trade leaves.
  • Send the client a short daily update with photos while the void is open.
  • Close the job with a single pack: schedule of works done, photos, certificates and any recommendations.

Firms that do this consistently tend to receive more voids, because a reliable turnaround is worth more to a landlord than a slightly lower price that comes with surprises.

Social housing voids and Awaab's Law

In the social rented sector in England, Awaab's Law has applied since 27 October 2025. Social landlords must investigate emergency hazards and carry out safety work within 24 hours of becoming aware of them[4], and must investigate potential significant hazards within 10 working days and complete safety work within 5 working days of the investigation ending[4]. A defect missed in a void becomes a hazard with a deadline the day the tenant moves in. Thorough void inspections protect the landlord and your contract. See our guides to Awaab's Law repairs and social housing contractor work.

Worked Example: a winter void

Example (fictional): a housing association hands a heating firm a two-bedroom flat in December for a four-week void with a new kitchen being fitted. The firm keeps the heating on frost protection, isolates the kitchen supply for the fitters and visits weekly.

In the Example, on the second visit the engineer finds the boiler locked out after a power cut and the flat at 6°C. He resets and checks it, runs every outlet and reports the lockout. At reinstatement he refills, flushes, recommissions and completes the gas safety check last. The flat is re-let on time, with no leaks found by the new tenant. For larger shared houses, see HMO plumbing and heating.

Frequently asked questions

Should a void property be drained down?

For long voids with nobody checking, usually yes. For short voids, or where works are on site, keep the heating on frost protection with weekly checks.

How do you stop pipes freezing in an empty house?

Keep the supplies on, set frost protection, lag exposed pipes and tanks, isolate outside taps and check the property weekly.

Is stagnant water in empty homes a legionella risk?

Yes. HSE says water should not stagnate, outlets should be used at least weekly, and long vacancies may need a flushing regime or draining[2].

When should the gas safety check be done on a void?

Last, after repairs, so the record reflects the system the tenant will use. The landlord must give the tenant the record before they move in[3].

References

  1. Department for Energy Security and Net Zero (2026). Energy Trends: UK gas, ET 4.1 natural gas supply and consumption (quarterly), September 2026 (opens in a new tab) ↑

  2. Health and Safety Executive (2026). Legionella and landlords’ responsibilities (opens in a new tab) ↑

  3. GOV.UK (2026). Your landlord's safety responsibilities (opens in a new tab) ↑

  4. Ministry of Housing, Communities and Local Government (GOV.UK) (2025). Awaab's Law: Guidance for social landlords - Timeframes for repairs in the social rented sector (opens in a new tab) ↑

  5. Health and Safety Executive (2026). Legionnaires’ disease: hot and cold water systems (opens in a new tab) ↑

Book a demo

See Ava handle your calls.

Book a short demo. We’ll walk through your calls and workflow, and agree what Ava should take care of.

Book a demo