Landlord commercial work

Awaab's Law and leaks: repair timescales for social landlords

Awaab's Law repair timescales for plumbing and heating contractors: emergency and significant hazards, the evidence landlords need and how to respond.

Ava research teamPublished 7 min read

On this page
  1. What Awaab's Law requires
  2. Two clocks: emergency and significant hazards
  3. Sorting plumbing faults into the right clock
  4. Leaks, damp and why landlords are nervous
  5. The evidence pack landlords now expect
  6. Attending an emergency hazard: a working sequence
  7. Example: a Friday evening leak
  8. Getting your firm ready for hazard work
  9. Contract terms to check before you sign
  10. Frequently asked questions
  11. References

Key takeaways

  • Awaab's Law applies to the social rented sector in England from 27 October 2025[1].
  • Emergency hazards, including broken boilers and significant leaks, must be investigated and made safe within 24 hours[2][3].
  • Significant hazards run on a 10 working day investigation clock and a 5 working day repair clock[4].
  • Contractors win or lose this work on evidence: timestamps, photos, readings and a clear make-safe note.
  • Leaks are a common route to damp, and damp affected 5% of homes in England in 2024[5].

What Awaab's Law requires

Awaab's Law is named after Awaab Ishak, a young child whose death in 2020 was caused by prolonged exposure to mould in his family's social rented home in Rochdale. It applies to the social rented sector in England from 27 October 2025[1], and it turns what used to be vague promises about repair times into legal deadlines.

The duty sits with the landlord: housing associations, councils and other registered providers. Plumbing and heating contractors are not named in the law, yet they do much of the work that decides whether a landlord meets it. Leaks, failed boilers, lost water supply and faulty gas appliances are all plumbing and heating problems, and the clock starts when the landlord becomes aware of the hazard, not when your engineer arrives.

Two clocks: emergency and significant hazards

For emergency hazards, landlords must investigate and carry out safety work within 24 hours of becoming aware of them[2]. For potential significant hazards, they must investigate within 10 working days and complete safety work within 5 working days of the investigation ending[4]. Government guidance gives broken boilers, gas or carbon monoxide leaks, total loss of water supply and significant leaks as examples of emergency hazards[3].

Awaab's Law timescales and the work they create
ClockLandlord mustTypical plumbing and heating triggersWhat you will be asked to do
Emergency hazardInvestigate and make safe within 24 hoursBroken boiler, gas or CO concern, no water at all, water coming through a ceilingAttend the same day, make safe, report findings and photos straight away
Significant hazard: investigationInvestigate within 10 working daysSlow leak behind a bath panel, damp patch near pipework, intermittent heating faultSurvey, test, write findings in plain English, recommend the safety work
Significant hazard: safety workComplete within 5 working days of the investigationReplace a leaking section, repair a failing cylinder, fix condensate or overflow issuesBook, complete and evidence the work inside the window

The 24-hour clock is measured in hours, not working days. A report at 6pm on a Saturday still has to be investigated and made safe by 6pm on Sunday.

Sorting plumbing faults into the right clock

Landlords decide the category, usually at the point of the call. Contractors can help by giving them clear criteria and by reporting quickly when what they find on site is worse, or better, than the call suggested. These are the questions that move a job between clocks:

  • Is any water reaching electrics, light fittings or sockets? Treat as emergency.
  • Has the household lost all heating or all hot water, and is anyone vulnerable or very young? Usually emergency, especially in cold weather.
  • Is there any smell of gas, a carbon monoxide alarm sounding or soot staining around an appliance? Emergency, and the gas emergency service may need to be involved.
  • Is the water supply completely off? Emergency. Low pressure alone is usually not.
  • Is there a slow, contained leak or damp staining with no immediate risk? Usually a significant hazard investigation.
  • Is there mould near pipework, a tank or a cylinder? Investigate the water source as well as the mould.

When carbon monoxide is suspected, the NHS advises people to stop using the suspect appliance, such as a boiler, and to get medical advice[6]. Your engineers should give that advice at the door and record that they gave it.

Leaks, damp and why landlords are nervous

Damp is common and rising. 5% of dwellings in England, about 1.4 million homes, had a damp problem in 2024, up from 4% in 2021 and 2022[5]. Not all of that is plumbing, since condensation and penetrating damp from outside play a large part, but a hidden leak can feed damp for months before anyone sees it.

Dwellings in England with a damp problemEnglish Housing Survey; 2024 equals about 1.4 million homes
Dwellings in England with a damp problemColumn chart. 2021: 4%; 2022: 4%; 2024: 5%.0%2%4%6%2021: 4%4%20212022: 4%4%20222024: 5%5%2024Dwellings in England with a damp problemColumn chart. 2021: 4%; 2022: 4%; 2024: 5%.0%2%4%6%2021: 4%4%20212022: 4%4%20222024: 5%5%2024

Source: Ministry of Housing, Communities and Local Government (GOV.UK), 2024[5]

Show the data
ItemValue
20214%
20224%
20245%

Social homes perform better than private lets on overall condition: 10% of social rented homes failed the Decent Homes Standard, against 22% of private rented homes[7]. Even so, landlords now face legal deadlines on every hazard, so expect more investigation orders, more photographs and more scrutiny of what your engineers write.

The evidence pack landlords now expect

Under these timescales the landlord must be able to prove what happened and when. Your paperwork becomes their defence. Build a standard close-out note that every engineer completes before leaving site:

  1. Arrival time and departure time, taken from the job system rather than typed by hand.
  2. What was reported, and what the engineer actually found.
  3. Readings where relevant: pressure drop test, flue gas analysis, moisture readings near the leak.
  4. Before and after photographs, with one wide shot showing the room.
  5. Make-safe action taken and the time it was completed.
  6. Permanent repair needed, parts required and a realistic date.
  7. Advice given to the tenant, including any instruction not to use an appliance.
  8. Whether anyone in the home appeared vulnerable, so the landlord can review priority.

Firms that send this pack within an hour of leaving site make the landlord's job easier, and they tend to keep the work. If you are building your first social housing relationship, our guide to working for housing associations explains how the work is bought and measured.

Attending an emergency hazard: a working sequence

  1. Confirm the job and the clock

    Note the time the landlord logged the report. Your target is that time plus 24 hours, minus whatever buffer the contract demands.

  2. Call ahead

    Ring the tenant to confirm access and give basic safety advice, such as turning off the stopcock or not using the boiler.

  3. Assess and make safe

    Isolate water, gas or electrics as needed, contain the leak, cap or disconnect faulty appliances and label them.

  4. Provide temporary measures

    Where heating or hot water is lost, agree temporary heaters or alternatives with the landlord if the permanent fix will take longer.

  5. Report before you leave the street

    Send the close-out note and photos. Flag clearly if the hazard is made safe but not fully resolved.

  6. Book the follow-on

    Order parts and propose a date for the permanent repair the same day, so the landlord can track it.

Example: a Friday evening leak

Example: at 7.10pm on a Friday, a tenant reports water dripping through the kitchen ceiling from the bathroom above. The landlord logs it as an emergency hazard and calls its out-of-hours contractor at 7.25pm. The engineer arrives at 9.05pm, finds a failed compression joint under the bath, isolates the supply to the bathroom, confirms the ceiling light circuit is dry with the tenant's help and fits a temporary repair. The close-out note, with six photographs and moisture readings, reaches the landlord at 10.15pm. On Monday a damp survey of the kitchen ceiling is booked as a separate investigation. The landlord can show an investigation and make-safe well within 24 hours, and a clear plan for what follows.

Getting your firm ready for hazard work

Awaab's Law work rewards firms that are organised before the phone rings. Three things decide whether you can hold a landlord's emergency clock without burning out your engineers.

  • Cover: a written out-of-hours rota with a named engineer and a named back-up for every night and weekend, plus a clear rule for when a second engineer is called in.
  • Stock: vans carrying the parts that resolve most make-safe visits, such as isolation valves, compression and push-fit fittings, pipe repair clamps, a spare pump head, common boiler fuses and sensors, temporary heaters and dust sheets.
  • Reporting: a job app or form that captures times, photographs and readings automatically, so the evidence pack is finished on site rather than typed up the next morning.

Train every engineer to describe findings in plain English. A landlord's surveyor, a tenant and sometimes a housing ombudsman case handler may all read the same note. Write what you saw, what you did and what is still needed, with no jargon and no guesses about cause that you cannot support.

Finally, review your first month of hazard jobs with the landlord's contract manager. Look at every job that came close to the deadline and agree what would have made it faster: better information at the point of call, earlier access arrangements or a different stock list.

Contract terms to check before you sign

  • Does the contract set internal targets shorter than the legal ones, and are they realistic for your patch?
  • Are there financial deductions for missed targets, and are they capped?
  • How are out-of-hours attendances priced, and is make-safe paid separately from the permanent repair?
  • Who decides the hazard category, and can you challenge a category that was wrong at the point of call?
  • What happens when you cannot get access? Agree a no-access process with evidence, so failed visits are not counted against you.

Many of these contracts are let through public procurement. For how notices and registration work, see our guides to finding public sector tenders and the Procurement Act for small contractors.

Frequently asked questions

Does Awaab's Law apply to private landlords?

It applies to the social rented sector in England, covering housing associations, councils and other registered providers. Check GOV.UK for any extension to other tenures before relying on it.

Does the 24-hour emergency clock pause at weekends?

No. The emergency timescale is counted in hours. The longer timescales for significant hazards are counted in working days.

Is a broken boiler always an emergency hazard?

Government guidance lists broken boilers as an example of an emergency hazard, but the landlord assesses each case. Cold weather and vulnerable occupants make an emergency category more likely.

What should an engineer do if the fault cannot be fixed in one visit?

Make the hazard safe, provide or arrange temporary measures, record what was done and when, and give the landlord a dated plan for the permanent repair.

References

  1. Ministry of Housing, Communities and Local Government (GOV.UK) (2025). Awaab's Law: Guidance for social landlords - Timeframes for repairs in the social rented sector (opens in a new tab) ↑

  2. Ministry of Housing, Communities and Local Government (GOV.UK) (2025). Awaab's Law: Guidance for social landlords - Timeframes for repairs in the social rented sector (opens in a new tab) ↑

  3. Ministry of Housing, Communities and Local Government (GOV.UK) (2026). Awaab's Law: Guidance for social landlords - Timeframes for repairs in the social rented sector (opens in a new tab) ↑

  4. Ministry of Housing, Communities and Local Government (GOV.UK) (2026). Awaab's Law: Guidance for social landlords - Timeframes for repairs in the social rented sector (opens in a new tab) ↑

  5. Ministry of Housing, Communities and Local Government (GOV.UK) (2024). English Housing Survey 2024 to 2025: Chapter 1, housing quality (opens in a new tab) ↑

  6. NHS (2026). Carbon monoxide poisoning (opens in a new tab) ↑

  7. Ministry of Housing, Communities and Local Government (GOV.UK) (2024). English Housing Survey 2024 to 2025: Chapter 1, housing quality (opens in a new tab) ↑