Key takeaways
- The grant is taken off the customer's price[1], so on a typical job most of the value can arrive from Ofgem after the work is finished[2][3].
- Redemption only starts after commissioning and the MCS installation certificate; approved claims are paid on Ofgem's weekly payment day, with occasional short delays[4].
- Deposits must respect the customer's cancellation rights on off-premises contracts[5][6].
- Work out how many grant jobs you can carry at once, and do not book more than that number.
Where the cash gap comes from
On a boiler swap, the customer pays you and you pay your supplier, often within a few weeks of each other. Grant-funded heat pump work breaks that pattern. The value of the Boiler Upgrade Scheme grant is taken off what the customer pays for the installation and shown on the quote and invoice[1]. You buy the heat pump, cylinder and materials, pay your team and any subcontractors, finish the job, and only then claim the grant from Ofgem.
The grant for an air or ground source heat pump is £7,500[2]. The median installed cost of an air-to-water heat pump under the scheme was £12,826 in July to September 2026, including the grant[3]. On a job at that median, the grant is about 58% of the job value, and the customer's own payment is about £5,326. In other words, more than half of a typical job's income arrives after the work is done.
The timeline you are working to
Ofgem's guidance sets the order. After the owner confirms consent and Ofgem's checks are complete, it emails you a voucher. From the voucher date you have 3 months to complete an air source installation, or 6 months for ground source[4]. Once you have commissioned the system and generated the MCS installation certificate, you apply to redeem the voucher, Ofgem runs final checks including the certificate details, and an approved redemption is processed for payment on the next scheduled payment day, which is weekly[4]. Ofgem asks scheme participants to note that there may occasionally be short delays and to plan accordingly[4].
The part of that timeline you control is the gap between commissioning and submitting the redemption. Every day the paperwork sits in a van is a day added to your cash gap.
Example: one job's cash flow
| Stage (Example) | Money in | Money out |
|---|---|---|
| Quote accepted, voucher applied for | None | None |
| Voucher issued, deposit taken | £1,500 deposit | None |
| Equipment ordered on 30-day account | None | None yet |
| Installation week | None | £1,800 labour and subcontract |
| Handover, balance invoiced | £3,826 balance | None |
| Supplier invoice due | None | £6,200 equipment and materials |
| Redemption approved and paid | £7,500 grant | None |
Example (fictional): in this job the firm is never out of pocket by more than a few thousand pounds, because the deposit covers labour and the supplier's 30-day terms push the largest payment past the customer's balance. Without the deposit and supplier terms, the firm would be about £8,000 out of pocket by the end of installation week. Multiply that by four jobs in progress, and the difference decides whether the business needs an overdraft.
Deposits and the customer's cancellation rights
Deposits are the first tool, but they must fit consumer law. For service contracts made off premises or at a distance, the customer's cancellation period ends 14 days after the contract is made[5], and you must not start work within that period unless the customer has expressly asked you to, on a durable medium for off-premises contracts[6]. A customer who cancels within the period is generally entitled to their money back, so treat a deposit taken in that window as refundable.
- Explain the deposit, what it pays for and when it becomes non-refundable in plain words on the quote.
- Take the deposit after the voucher is issued, so a refused application does not leave you holding a customer's money.
- Order equipment after the cancellation period has passed, unless the customer has asked you in writing to start sooner.
- Consider stage payments on larger jobs, linked to clear milestones such as equipment delivery and commissioning.
Supplier terms and ordering
Your supplier is the second lever. A trade account with 30 or 60-day terms can carry most of the gap if you time orders well. Ask your main heat pump supplier for terms that match the scheme timeline, and show them your redemption record once you have a few jobs completed. Some suppliers will also hold stock for named jobs, which lets you confirm availability without paying early.
Avoid ordering ahead of the voucher. A heat pump sitting in your unit for a customer whose voucher has not been issued is cash you cannot use and a product you may struggle to return.
Know how many jobs you can carry
Find your worst-case gap per job
Add equipment, materials, labour and subcontract costs, then subtract the deposit and balance you will have received before they fall due.
Add a delay margin
Assume redemption takes longer than usual for some jobs, as Ofgem warns can happen.
Check your available cash
Use cash at bank plus any agreed overdraft, after wages, VAT and other bills.
Divide
Available cash divided by the worst-case gap gives the number of grant jobs you can have open at once.
Book to that number
Schedule installs so you never exceed it, and revisit the number monthly.
This calculation is simple but most firms never do it, and discover their limit only when a supplier invoice and payroll fall in the same week as a delayed redemption.
Borrowing to bridge the gap
Construction businesses already lean on short-term finance: 47% of construction SME employers used credit cards as a source of finance in 2025, second only to transport and storage[7]. A credit card can cover a short gap, but it is an expensive way to fund a growing heat pump business. An agreed overdraft or a facility from your bank, sized to the calculation above, is usually cheaper and easier to plan around. Talk to your bank before you need it, with your job pipeline and redemption record in hand.
Late payment pressure across the sector
Cash flow is a wider problem for the trades. 45% of construction SME employers named late payment as a major obstacle in 2025, up from 36% in 2024 and the highest of any sector[8]. Grant redemption is not late payment, but it adds to the same pressure, and firms that also wait on builders or landlords can find several delays arriving at once.
Source: Department for Business and Trade (GOV.UK), 2025[8]
Show the data
| Item | Value |
|---|---|
| 2024 | 36% |
| 2025 | 45% |
Warning signs to act on early
Cash problems in a growing heat pump business rarely arrive without warning. They show up first in small habits: a director paying suppliers late to cover wages, redemptions that sit unsubmitted for days, or deposits being used to fund jobs other than the one they were taken for. Spot these early and they are easy to fix; ignore them and they compound as volume grows.
- Open grant redemptions add up to more than a month's wage bill.
- You are ordering stock for the next job using the deposit from the job after it.
- More than one voucher is within a few weeks of expiry without an install date.
- Supplier statements show overdue invoices you had planned to pay from a grant.
- You are turning down boiler work to fit in more grant installs than your cash calculation allows.
If two or more apply, slow your booking rate for a month, clear the redemptions and rebuild your margin before taking on more. Boiler servicing and repairs are paid faster, and keeping them going while the heat pump side grows is one of the simplest ways to protect cash flow.
Habits that shorten the gap
- Register the MCS installation certificate on handover day, not at the end of the week.
- Submit the redemption as soon as the certificate is generated, and check the details match the voucher before you do.
- Invoice the customer's balance at handover, with payment due on completion.
- Keep a weekly list of open vouchers, their expiry dates and redemption status.
- Chase any redemption that has not been approved within your usual time, rather than waiting.
These habits cost nothing and, across a year of jobs, can be worth more than a better supplier discount. They also make you a lower-risk customer for your bank and your suppliers, which helps when you want to grow.
Frequently asked questions
How long does it take to get the Boiler Upgrade Scheme grant paid?
After commissioning and the MCS installation certificate, you apply to redeem the voucher. Ofgem processes approved redemptions on its next weekly payment day, with occasional short delays.
Can I take a deposit on a grant-funded job?
Yes, but respect the customer's 14-day cancellation rights on off-premises and distance contracts, and explain clearly when the deposit becomes non-refundable.
Should I order the heat pump before the voucher is issued?
Avoid it. If the voucher is refused or delayed, you are left holding stock and cash you cannot use.
How many grant jobs can I run at once?
Divide your available cash by the worst-case cash gap per job, after deposits, balances and supplier terms.
References
GOV.UK (2026). Apply for the Boiler Upgrade Scheme: how to apply (opens in a new tab) ↑
GOV.UK (2026). Apply for the Boiler Upgrade Scheme: what you can get (opens in a new tab) ↑
Department for Energy Security and Net Zero (2026). Boiler Upgrade Scheme (BUS) monthly statistics: England and Wales, September 2026 (opens in a new tab) ↑
Ofgem (2026). Boiler Upgrade Scheme (BUS): installers (opens in a new tab) ↑
legislation.gov.uk (The National Archives) (2013). The Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013, regulation 30 (opens in a new tab) ↑
legislation.gov.uk (The National Archives) (2013). The Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013, regulation 36 (opens in a new tab) ↑
Department for Business and Trade (GOV.UK) (2025). Longitudinal Small Business Survey 2025: SME employers (businesses with 1 to 249 employees) (opens in a new tab) ↑
Department for Business and Trade (GOV.UK) (2025). Longitudinal Small Business Survey 2025: SME employers (businesses with 1 to 249 employees) (opens in a new tab) ↑