Heat pumps low carbon

Boiler Upgrade Scheme: an installer's walkthrough

A step-by-step Boiler Upgrade Scheme walkthrough for installers: eligibility checks, the voucher application, install deadlines, redemption and payment.

Ava research teamPublished 6 min read

On this page
  1. What the scheme pays and where
  2. Check eligibility before you quote
  3. The walkthrough, step by step
  4. Deadlines and who acts
  5. Chasing the owner's consent
  6. Pricing in context
  7. What to tell the customer at each stage
  8. Example: an air source job from survey to payment
  9. Why applications and redemptions get held up
  10. Before your first application
  11. Frequently asked questions
  12. References

Key takeaways

  • The scheme pays £7,500 towards an air or ground source heat pump in England and Wales, plus £1,500 for off-gas oil and LPG homes until March 2027[1][2].
  • Check eligibility before you quote: what the system replaces, the EPC, the product list, full space heating sizing and no other public grant[3].
  • Once the voucher is issued you have 3 months to finish an air source install, 6 for ground source[3].
  • Redemption needs the MCS installation certificate, and approved claims are paid on Ofgem's weekly payment day[3].

What the scheme pays and where

The Boiler Upgrade Scheme gives £7,500 towards an air source heat pump and £7,500 towards a ground source heat pump[1]. It also offers £5,000 towards a biomass boiler and £2,500 towards an air-to-air heat pump[4]. Until March 2027, homes heated by oil or LPG with no mains gas connection can get an extra £1,500 towards an air or ground source heat pump[2]. The scheme is open in England and Wales; Scotland has separate loans and grants, and Northern Ireland's Boiler Replacement Scheme is closed[5].

For the customer the grant is simple: the value is taken off what they pay, and it appears on the quotation and the invoice[6]. For you it is a process with deadlines, eligibility rules and a payment you wait for. This walkthrough follows a typical air source job from first enquiry to payment.

Check eligibility before you quote

Homeowners are told that their installer will confirm whether they are eligible[6], so the check is yours. Get it wrong and you have a signed customer, an ordered heat pump and no voucher. Run through these points at survey and record the evidence.

  • The new system must replace an existing fossil fuel or electric heating system, with exceptions such as eligible self-builds[3].
  • If the property has a valid Energy Performance Certificate, you must provide its number; if not, you need alternative evidence of eligibility[3].
  • The heat pump must meet the published standards; the Boiler Upgrade Scheme Product Eligibility List, a subset of the MCS product list, helps you check[3].
  • The heat pump must be sized to meet the full space heating needs of the property, even if a supplementary appliance is also fitted[3].
  • The system must not be a hybrid that combines a heat pump with fossil fuel heating[3].
  • The owner must not have received another public grant towards the cost, and the system must not be funded by ECO[3].

The walkthrough, step by step

  1. Survey and design

    Do the heat loss and design, confirm eligibility and choose a product on the eligibility list.

  2. Quote with the grant shown

    Show the full price, the grant deduction and the customer's balance on the quotation[6].

  3. Agree and apply

    Once the customer accepts, apply for the voucher on their behalf on the Ofgem website[6].

  4. Owner consent

    Ofgem emails the property owner to confirm they consent to you applying and to confirm some eligibility details[3].

  5. Voucher issued

    After its checks, Ofgem emails you a voucher for the grant amount[3].

  6. Install and commission

    Complete the installation within 3 months of the voucher date, or 6 months for ground source[3].

  7. MCS certificate

    Register the installation and generate the MCS installation certificate.

  8. Redeem

    Apply to Ofgem to redeem the voucher; it checks eligibility again, including the certificate details[3].

  9. Get paid

    Approved redemptions are processed for payment on the next scheduled payment day, which is weekly[3].

Deadlines and who acts

Boiler Upgrade Scheme stages and deadlines from Ofgem's installer guidance[3]
StageWho actsWatch for
Voucher applicationInstallerComplete EPC or alternative evidence and product details
Consent confirmationProperty ownerOwner not replying to Ofgem's email
Installation windowInstaller3 months for air source, 6 for ground source, from voucher issue
Expired voucherInstallerYou can re-apply for a new voucher
RedemptionInstallerMCS installation certificate details must match
PaymentOfgemWeekly payment days, with occasional short delays

If a voucher expires before you have commissioned the installation, you can re-apply for another one[3], but that adds time and risk. Plan the install date before you apply, especially in winter, and check your supply of equipment so a delayed delivery does not push the job past the deadline.

The most avoidable delay is the owner not responding to Ofgem's consent email. Tell the customer at the quote stage that the email will come, who it will come from and that nothing can happen until they reply. Ask them to check spam folders. A short text from you on the day you submit the application, reminding them to look out for it, saves days.

Ofgem may also phone or visit the property to check the installation, and MCS may contact the owner for its own checks[6]. Mention both at handover so a call from either is not a surprise and the customer does not think it is a scam.

Pricing in context

Median installed costs under the scheme give a useful reference point when customers compare quotes. In July to September 2026, the median cost of an air-to-water heat pump was £12,826 and of a ground source heat pump £34,630, both including the grant[7]. Your price will depend on the property, the emitters and the hot water work, but being able to say where you sit against the national median helps customers understand a quote.

Median installed cost under the Boiler Upgrade Scheme, July to September 2026Including the grant
Median installed cost under the Boiler Upgrade Scheme, July to September 2026Comparison. Air-to-water heat pump: £12,826; Ground source heat pump: £34,630.£12,826Air-to-water heat pumpAir-to-water heat pump: £12,826£34,630Ground source heat pumpGround source heat pump: £34,630Median installed cost under the Boiler Upgrade Scheme, July to September 2026Comparison. Air-to-water heat pump: £12,826; Ground source heat pump: £34,630.£12,826Air-to-water heat pumpAir-to-water heat pump: £12,826£34,630Ground source heat pumpGround source heat pump: £34,630

Source: Department for Energy Security and Net Zero, 2026[7]

Show the data
ItemValue
Air-to-water heat pump£12,826
Ground source heat pump£34,630

Demand is rising. September 2026 had 9,738 applications, 30% more than August and the highest monthly total since the scheme began[8]. Busy months can mean slower processing, so build a margin into the dates you promise customers.

What to tell the customer at each stage

Customers find the scheme reassuring until something stalls, and then they ring you. A short message at each stage keeps them informed and cuts those calls. Send it by the channel the customer chose at the quote stage.

  1. After acceptance: we have applied for your grant; Ofgem will email you to confirm, so please reply as soon as it arrives.
  2. Voucher issued: your grant is confirmed and we have booked your installation for the agreed date.
  3. Before installation: what will happen on each day, when heating and hot water will be off and what we need from you.
  4. After commissioning: your system is registered with MCS and you will receive the certificate; Ofgem or MCS may contact you to check the installation.
  5. After payment: your grant has been redeemed and your account with us is settled.

These five messages take minutes to set up as templates and make the process feel organised from the customer's side, which is what they remember when they recommend you.

Example: an air source job from survey to payment

Example (fictional): a heating firm surveys a gas-heated semi in early March, confirms the EPC number and designs a system using a heat pump on the eligibility list. The quote shows the full price, the £7,500 grant and the customer's balance. The customer accepts and the firm applies the same week, texting the customer to watch for Ofgem's email.

The owner confirms consent within two days and the voucher arrives the following week. The firm books the install for late April, comfortably inside the three-month window, commissions it, registers the MCS certificate and submits the redemption the day after handover. The payment arrives on a weekly payment day soon after approval. The firm's job sheet records every date, so its office can see how long each stage took and quote realistic dates next time.

Why applications and redemptions get held up

  • Missing or wrong EPC number, or no alternative evidence where there is no valid EPC.
  • A product that is not on the eligibility list for the scheme.
  • A design that relies on a boiler to meet part of the space heating demand.
  • Details on the MCS certificate that do not match the voucher application.
  • A voucher that expired because the install slipped.
  • An owner who has already had another public grant towards the work.

Ofgem has the power to audit installers and installations and to act where it suspects or finds ineligibility or non-compliance; audits can be on site or at a desk, at any point after you apply, including after you have been paid[3]. Keep the survey, design, EPC evidence, product details, commissioning records and consent trail together for every job, so an audit request takes minutes to answer.

Before your first application

Set up your installer account with Ofgem, make sure your MCS certification or umbrella arrangement covers the technology, and write a one-page internal checklist covering the points above. Then read Boiler Upgrade Scheme rule changes so your quotes reflect the current rules, and managing cash flow while vouchers are redeemed so the wait for payment does not catch you out.

Frequently asked questions

Who applies for the Boiler Upgrade Scheme grant?

The MCS certified installer applies on the property owner's behalf, and Ofgem asks the owner to confirm consent.

How long do I have to install after the voucher is issued?

Three months for an air source heat pump and six months for a ground source heat pump.

When is the grant paid?

After commissioning and the MCS installation certificate, you apply to redeem the voucher. Approved redemptions are paid on Ofgem's next weekly payment day.

Can a hybrid heat pump get the grant?

No. The scheme excludes systems that combine a heat pump with fossil fuel heating.

References

  1. GOV.UK (2026). Apply for the Boiler Upgrade Scheme: what you can get (opens in a new tab) ↑

  2. GOV.UK (2026). Apply for the Boiler Upgrade Scheme: what you can get (opens in a new tab) ↑

  3. Ofgem (2026). Boiler Upgrade Scheme (BUS): installers (opens in a new tab) ↑

  4. GOV.UK (2026). Apply for the Boiler Upgrade Scheme: what you can get (opens in a new tab) ↑

  5. GOV.UK (2026). Apply for the Boiler Upgrade Scheme (opens in a new tab) ↑

  6. GOV.UK (2026). Apply for the Boiler Upgrade Scheme: how to apply (opens in a new tab) ↑

  7. Department for Energy Security and Net Zero (2026). Boiler Upgrade Scheme (BUS) monthly statistics: England and Wales, September 2026 (opens in a new tab) ↑

  8. Department for Energy Security and Net Zero (2026). Boiler Upgrade Scheme (BUS) monthly statistics: England and Wales, September 2026 (opens in a new tab) ↑

Book a demo

See Ava handle your calls.

Book a short demo. We’ll walk through your calls and workflow, and agree what Ava should take care of.

Book a demo