Key takeaways
- Link every payment to a stage the customer can see, so you are never far ahead on materials and labour and they are never paying for work not yet done.
- Late payment is rising: 45% of construction SME employers called it a major obstacle in 2025, up from 36%[1].
- The Construction Act payment rules do not apply to contracts with residential occupiers[2], so a domestic schedule must be written into your own terms.
- On business-to-business work you can claim statutory interest of 8% plus base rate on late payments[3].
- Say what happens if a stage payment is late before the job starts, not when it happens.
Why bigger jobs need a schedule
On a one-day repair, payment on completion is simple. On a bathroom refit, a system conversion or a heat pump install, you may buy several thousand pounds of materials and spend two weeks on site before the job is finished. If the whole price is due at the end, you are lending the customer money, and you carry all the risk if they delay, dispute or disappear.
Stage payments share that risk fairly. The customer pays as visible progress is made; you are never too far ahead on what you have spent. Done well, it also helps the customer, who can see what each payment buys and is never asked to pay for work that has not happened.
Late payment is getting worse
Construction firms feel late payment more than any other sector. In 2025, 45% of construction SME employers named late payment as a major obstacle to their business, up from 36% a year earlier and the highest of any sector[1]. Across all UK SME employers that gave trade credit, 63% said late payment was a problem[4].
Source: Department for Business and Trade (GOV.UK), 2025[1]
Show the data
| Item | Value |
|---|---|
| 2024 | 36% |
| 2025 | 45% |
Domestic customers are usually better payers than main contractors, but bigger jobs bring bigger sums and more opportunities for a dispute to hold up the final payment. A schedule agreed at the start is the cheapest protection you can buy.
Principles of a fair schedule
- Tie each payment to a stage both sides can recognise: materials delivered, first fix complete, boiler commissioned, tiling finished.
- Keep the deposit in line with the materials you must order specifically for this job, not with your general cash needs.
- Make sure that at every point the customer has paid roughly for what has been delivered, not far more.
- Hold back a modest final payment for completion and handover, so the customer has an incentive to sign off and you have an incentive to finish snags quickly.
- Agree how variations are added: usually to the next stage payment after they are approved.
Avoid schedules that ask for most of the price before any work is done. They are hard to justify to a customer, they look like a warning sign to anyone reading reviews of firms that went bust mid-job, and they can be challenged as unfair.
Example schedules by job type
| Job (Example) | Deposit | Interim stage | Second stage | On completion |
|---|---|---|---|---|
| Combi replacement, 1 to 2 days | Optional, for boiler order | None | None | Balance on commissioning |
| System to combi conversion, 3 to 4 days | 25% for materials | None | None | 75% on commissioning |
| Bathroom refit, 2 to 3 weeks | 20% for suite and materials | 30% at first fix complete | 40% at tiling complete | 10% at handover |
| Heat pump install | 25% for equipment | 35% at external unit and pipework installed | 30% at commissioning | 10% at handover with documents |
| Small commercial refurbishment | None or per contract | Monthly valuations | Monthly valuations | Final account, less any agreed retention |
In each Example, the deposit covers materials ordered for that customer, and later payments follow work that the customer can see. Adjust the percentages to fit your own costs: if a heat pump and cylinder account for most of the price, the equipment stage will be larger.
Domestic and commercial rules are different
Commercial construction contracts carry statutory payment rules, including rights to interim payments and payment notices, under the Housing Grants, Construction and Regeneration Act 1996. Those rules do not apply to a construction contract with a residential occupier, meaning a contract that principally relates to work on a dwelling one of the parties lives in or intends to live in[2]. For most domestic jobs, then, the only payment schedule is the one you write into your quote and terms.
On business-to-business work, including jobs for landlords trading as companies, managing agents and commercial clients, you can claim statutory interest on late payments of 8% plus the Bank of England base rate[3]. Many small firms never use it, but saying in your terms that you will is often enough to move an invoice up the pile.
Write the schedule into the quote
List the stages
Name each stage in words the customer understands, with the amount or percentage due.
Define ‘complete’
For each stage, say what complete means: ‘first fix complete: all supply and waste pipework installed and pressure tested, ready for boarding’.
Set the payment period
For example, payment due within three days of the stage invoice, by bank transfer or card.
Say what happens if it is late
Work on the next stage will pause until the payment clears; you will tell the customer in writing before pausing.
Explain variations
Approved extra work is added to the next stage invoice.
Confirm the final payment
Due on completion and handover, with any snags listed and a date agreed to fix them.
Send each stage invoice the day the stage is reached, with a photo of the completed work. Customers pay faster when the invoice arrives while the progress is fresh in their mind.
Taking the payments safely
Stage payments mean several transfers of large sums, which makes them attractive to fraudsters who intercept emails and send customers fake bank details. A customer who pays the wrong account will still expect the job finished, so protect both of you.
- Give your bank details once, in the quote, and tell the customer you will never change them by email.
- Ask customers to confirm the account by phone before their first transfer, using the number on your van or website rather than one in an email.
- Send a receipt for every stage payment on the day it clears, showing what has been paid and what remains.
- Offer card payment for customers who prefer it, and build any card charges into your prices rather than surprising them with a surcharge.
- Keep stage invoices numbered in sequence so the final account is easy to reconcile.
Answering customer objections to stage payments
Some customers are uneasy about paying before the job is done, often because they have read stories about firms disappearing with deposits. Answer the concern directly rather than defending your terms.
- ‘Why do you need money up front?’ ‘The deposit covers the suite and materials we order just for you. You will see them delivered before we start.’
- ‘Can I pay everything at the end?’ ‘On a job this size we work in stages, so you never pay for work you haven't seen. Each payment follows a stage you can check.’
- ‘What if something goes wrong?’ ‘The last payment is due at handover, after we've fixed any snags together.’
When a stage payment is late
- Day one: a friendly reminder by text or email with the invoice attached. Most late payments are forgotten, not refused.
- Day three: a phone call. Ask if there is a problem with the work. If there is, deal with it; if not, agree a date.
- Day five: written notice that work on the next stage will pause from a stated date if payment has not cleared, as your terms set out.
- If the customer raises a genuine complaint, separate it from the payment: fix the problem and invoice the undisputed amount.
Pausing a job is a last resort, and it must be in your terms before you use it. Leave the property safe, with water and heating working wherever possible, and confirm everything in writing.
Keep cancellation rights in mind
If the contract is agreed away from your premises, for example at the customer's kitchen table after a survey, the customer has a 14-day cancellation period[5]. A deposit taken during that period may have to be refunded if they cancel. If they ask you to start within the 14 days, record that request; it affects what they owe if they later cancel. This is one reason to keep deposits linked to materials you will genuinely need to order.
Example: a bathroom schedule that worked
Example (fictional): a firm in Exeter used a four-stage schedule on a bathroom refit: 20% deposit, 30% at first fix, 40% after tiling and 10% at handover. The customer approved a variation for an electric towel rail, which was added to the tiling invoice. Every stage invoice went out the same day with photos. The customer paid each one within two days, and the final 10% was paid the evening of the handover.
A good schedule is boring: everyone knows what is due, when and why, and nobody has to chase.
Frequently asked questions
How much deposit should a plumber take on a bathroom?
Enough to cover materials ordered specifically for the job, often a fifth to a quarter of the price. Later payments should follow visible stages of work.
Do the Construction Act payment rules apply to domestic jobs?
Not to a construction contract with a residential occupier[2]. Your stage payments must be written into your own quote and terms.
Can I stop work if a stage payment is late?
Only if your terms allow it. Give written notice first, leave the property safe and working where possible, and resolve any genuine complaint separately.
Can I charge interest on late payments?
On business-to-business work, yes: statutory interest of 8% plus base rate[3]. For domestic customers, any interest must be in your agreed terms and fair.
References
Department for Business and Trade (GOV.UK) (2025). Longitudinal Small Business Survey 2025: SME employers (businesses with 1 to 249 employees) (opens in a new tab) ↑
legislation.gov.uk (The National Archives) (1996). Housing Grants, Construction and Regeneration Act 1996, section 106 (residential occupiers) (opens in a new tab) ↑
GOV.UK (2026). Late commercial payments: charging interest (opens in a new tab) ↑
Department for Business and Trade (GOV.UK) (2025). Longitudinal Small Business Survey 2025: SME employers (businesses with 1 to 249 employees) (opens in a new tab) ↑
legislation.gov.uk (The National Archives) (2013). The Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013, regulation 30 (opens in a new tab) ↑