Key takeaways
- In new dwellings and material changes of use, water delivered to a fixed bath must not exceed 48°C[1].
- Where vulnerable people bathe, HSE says water for whole-body immersion must not exceed 44°C[2].
- Legionella control needs stored water at 60°C and hot outlets reaching 50°C within a minute[3], which is why mixing happens at the point of use.
- HSE expects TMVs and outlet temperatures to be monitored and maintained so the controls stay effective[2].
Two hazards, one valve
Hot water systems have to balance two risks that pull in opposite directions. Legionella bacteria need to be controlled by heat: HSE's guidance says hot water should be stored at 60°C or above and should reach at least 50°C within one minute at outlets[3]. Water at those temperatures can scald, especially young children, older people and anyone with reduced sensation or mobility.
A thermostatic mixing valve resolves that tension. It blends hot and cold water close to the outlet and holds the mixed temperature steady even when supply pressures or temperatures change, shutting down if the cold supply fails. HSE's guidance on scalding is explicit that any precautions taken should not introduce other risks, for example from legionella[2]. Storing hot and blending late is how you meet both aims.
Where a TMV is required, and where it is wise
| Setting | What the rules say | What that means for you |
|---|---|---|
| New dwelling or material change of use, fixed bath | Water delivered to the bath must not exceed 48°C | Fit a device such as a TMV on the bath supply and commission it to 48°C or below |
| Care homes and settings with vulnerable people, baths and showers | Water for whole-body immersion must not exceed 44°C where vulnerable people are at risk | TMVs on baths and showers, commissioned and maintained to 44°C or below |
| NHS settings, electric showers | HSE notes a maximum of 41°C required in the NHS | Check the client's own policy and healthcare guidance |
| Existing homes | No general legal requirement for a replacement bath | Recommend a TMV where children, older or disabled people live |
The Building Regulations requirement comes from G3(4): the hot water supply to any fixed bath must be designed and installed so that the water that can be delivered to that bath does not exceed 48°C[1]. It applies only when a dwelling is erected or formed by a material change of use[1]. Installing a bathroom that involves plumbing can also need building regulations approval in England, which a competent person scheme member can self-certify[4].
In health and social care, HSE's guidance goes further. Where vulnerable people are at risk from scalding during whole-body immersion, water temperatures must not exceed 44°C, and where storage or distribution temperatures are high, baths and showers should be fitted with TMVs to keep water at or below that level[2]. For basins, HSE says the risk is lower, but where someone is vulnerable, adequate controls on output temperature, such as TMVs, should be in place[2].
Source: Health and Safety Executive, 2026[2]
Show the data
| Item | Value |
|---|---|
| Electric showers in the NHS (maximum) | 41 °C |
| Accessible hot surfaces (maximum) | 43 °C |
| Whole-body immersion for vulnerable people (maximum) | 44 °C |
Choosing the right valve
- Match the valve's performance designation to the setting: valves certified for healthcare use are tested to a stricter specification than domestic ones.
- Check the supply conditions: high or low pressure, balanced or unbalanced, gravity or mains, and the minimum flow the valve needs.
- Confirm the valve carries a recognised water regulations approval for the way you will install it.
- Choose a valve with integral strainers and check valves, or plan to fit them, so debris and cross-flow do not upset the mix.
- For multiple outlets from one valve, check the manufacturer allows it and that pipe runs after the valve are short.
Valves built into bath fillers or shower mixers can meet the requirement if their certification covers the use. Separate in-line TMVs are easier to service and are the usual choice in care settings, where access for maintenance matters more than appearance.
Installation points that save trouble later
- Fit isolation valves on both inlets so the TMV can be serviced without draining the system.
- Install the valve as close to the outlet as the manufacturer recommends, to limit the length of blended water pipework.
- Leave an access panel; a valve that cannot be reached will not be serviced.
- Flush supply pipework thoroughly before connecting the valve to avoid debris in the cartridge.
- Label the valve with its location and set temperature for the maintenance log.
Commissioning, step by step
Record supply conditions
Measure hot and cold supply temperatures and pressures at the valve inlets. These are your baseline for later checks.
Set the mixed temperature
Adjust the valve to the required maximum for the setting, such as 48°C for a new dwelling bath or 44°C for a care home bath, using a calibrated thermometer at the outlet.
Check stability
Open and close other outlets on the same supplies and confirm the mixed temperature stays stable.
Test the fail-safe
Isolate the cold supply and confirm the valve shuts off or reduces flow to a safe trickle as the manufacturer specifies. Restore the supply and recheck the temperature.
Record and hand over
Write down the set temperature, supply readings, fail-safe result and date, and give the owner a copy with the maintenance schedule.
Annual checks and servicing
HSE's guidance is short and firm: outlet temperatures and TMVs should be monitored and maintained to ensure the controls are effective[2]. Most manufacturers and certification schemes recommend an early in-service check after commissioning and then regular checks at intervals based on what you find. Agree the interval with the client in writing, and shorten it where water is hard or results drift.
- Measure the mixed outlet temperature and compare it with the commissioning record.
- If it has moved, find out why before adjusting: check supply temperatures, strainers and check valves.
- Isolate, remove and clean strainers and filters; descale or replace the cartridge as the manufacturer advises.
- Repeat the fail-safe test with the cold supply isolated.
- Re-set if needed, record all readings and note any parts replaced.
A valve that keeps drifting is telling you something. Hard water, debris from old pipework or a failing check valve are the usual causes. Replacing the cartridge without fixing the cause means a callback within months.
Common faults and their causes
- Mixed temperature creeping up over months: usually scale on the thermostatic element or a partly blocked cold strainer.
- Temperature swinging when other taps are used: unbalanced supplies, undersized pipework or a failing check valve.
- Poor flow at the outlet: blocked strainers or a valve below its minimum operating flow.
- No shut-off on the fail-safe test: a worn cartridge or debris holding the shuttle open, which needs immediate attention.
- Hot water appearing at a cold tap nearby: cross-flow through a failed check valve inside the TMV.
Record which fault you found and what fixed it. Over a few years the log shows which valves, sites and water conditions need closer attention.
Hot surfaces are part of the same risk
Scald risk is not only about water. HSE's guidance for health and social care settings says that where people could come into contact with hot pipes or radiators, the surface should not exceed 43°C when the system is running at its maximum design output[2]. When you install or service TMVs in a care home, look at exposed pipework and radiators in the same rooms and recommend guards or low-surface-temperature emitters where needed.
Example: a small care home contract
Example: a plumbing firm wins the maintenance contract for a twelve-bed care home in Norwich. The home has a stored hot water system at 60°C and TMVs on every bath, shower and basin used by residents. The firm's first visit finds two bath valves delivering above 44°C and one with no fail-safe response. The service records show no checks for over a year.
The firm replaces the faulty cartridge, cleans all strainers, re-commissions every valve and creates a log for each outlet with location, set temperature and supply readings. It agrees a schedule of checks with the manager, with closer intervals for the two valves that drifted. Six months later both are still holding temperature, and the home's inspection paperwork includes a complete TMV record for the first time.
Records to leave behind
- A TMV schedule listing each valve, its location, outlet served and set temperature.
- Commissioning sheets with supply temperatures and pressures and fail-safe results.
- A service log with each check date, readings, actions and parts replaced.
- The manufacturer's maintenance instructions for each valve type.
In homes, combination boilers deliver hot water on demand, but heat pump and cylinder systems store it. In England 19% of homes had a condensing boiler other than a combination boiler in 2024[5], and many of those feed cylinders, so ask about blending whenever you work on stored hot water.
Frequently asked questions
Is a TMV a legal requirement on every bath?
No. Part G requires bath water to be limited to 48°C in new dwellings and material changes of use. In existing homes it is not generally required, but it is often recommended.
What temperature should a care home bath TMV be set to?
HSE says that where vulnerable people are at risk during whole-body immersion, water temperatures must not exceed 44°C.
How often should TMVs be serviced?
HSE expects TMVs to be monitored and maintained so they remain effective. Follow the manufacturer's schedule and adjust intervals based on results and water hardness.
Does a TMV increase legionella risk?
It can if blended water pipework is long or rarely used. Fit valves close to outlets, keep blended runs short and flush little-used outlets.
References
legislation.gov.uk (The National Archives) (2010). The Building Regulations 2010, Schedule 1, Part G (opens in a new tab) ↑
Health and Safety Executive (2026). Scalding and burning (opens in a new tab) ↑
Health and Safety Executive (2026). Legionella: things to consider for hot and cold water systems (opens in a new tab) ↑
GOV.UK (2026). Building regulations approval (opens in a new tab) ↑
Ministry of Housing, Communities and Local Government (GOV.UK) (2024). English Housing Survey 2024 to 2025: Chapter 2, energy efficiency (opens in a new tab) ↑