Payment terms with main contractors: what to negotiate

What plumbing and heating subcontractors should negotiate in main contractor payment terms: due dates, payment notices, suspension and interest.

Ava research teamPublished 7 min read

On this page
  1. Why payment terms deserve as much attention as price
  2. The payment cycle in plain English
  3. What applies if the contract is silent
  4. Rights the contract cannot take away
  5. What to negotiate before you sign
  6. Red flags in a main contractor's terms
  7. Example: a monthly payment timeline
  8. Templates you can adapt
  9. A monthly cash routine for contract work
  10. Frequently asked questions
  11. References

Key takeaways

  • The Construction Act gives subcontractors rights the contract cannot remove: stage payments, payment notices and the right to suspend for non-payment[1].
  • If the contract is silent, the statutory Scheme sets payment due 7 days after the period and the final date 17 days after that[2].
  • A pay less notice must reach you before the final date; without one, the notified sum is due in full[1][2].
  • Late payment is the top obstacle for construction SMEs, so negotiate dates before you price[3].
  • You can suspend work after giving at least seven days' notice, and claim statutory interest on late business debts[1][4].

Why payment terms deserve as much attention as price

A good rate on a bad payment cycle can still sink a small firm. On a main contractor's site you pay engineers weekly and merchants monthly, while the money for the work you did this month may not arrive for eight weeks or more. 45% of construction SME employers named late payment as a major obstacle in 2025, up from 36% in 2024[3], and 47% used credit cards as a source of finance[5].

The good news is that most subcontracts for plumbing and heating on construction projects are construction contracts under the Housing Grants, Construction and Regeneration Act 1996, usually called the Construction Act. It gives you a set of rights, and where the contract does not meet the Act's requirements, the statutory Scheme for Construction Contracts fills the gaps.

The payment cycle in plain English

Key payment terms in a construction subcontract
TermWhat it meansWhy it matters to you
Valuation or application dateThe date you apply for payment for work done in the periodMiss it and your work rolls into next month
Due dateThe date the payment becomes dueStarts the clock for notices
Payment noticeNotice of the sum the payer considers due and how it was calculatedMust be given within five days of the due date
Pay less noticeNotice that the payer intends to pay less than the notified sum, and whyMust arrive before the final date for payment
Final date for paymentThe last day the payer can pay without being in defaultAfter this you can suspend and claim interest

The Act requires the contract to provide for a payment notice not later than five days after the payment due date, setting out the sum considered due and the basis of calculation[1]. If the payer wants to pay less than the notified sum, it must give a pay less notice before the prescribed period ahead of the final date; otherwise the notified sum must be paid on or before the final date[1].

What applies if the contract is silent

Where the contract does not set compliant payment terms, the Scheme applies. For stage payments, payment becomes due on the later of 7 days after the end of the relevant period or the making of a claim by the payee[2]. The final date for payment is 17 days from the date payment becomes due[2]. A pay less notice must be given not later than seven days before the final date for payment, unless the parties agreed a different period[2].

Scheme default payment timeline for stage paymentsDays after the end of the payment period, where the contract does not set its own terms
Scheme default payment timeline for stage paymentsColumn chart. Payment due: 7 days; Latest pay less notice: 17 days; Final date for payment: 24 days.0 days10 days20 days30 daysPayment due: 7 days7 daysPayment dueLatest pay less notice: 17 days17 daysLatest pay less noticeFinal date for payment: 24 days24 daysFinal date for paymentScheme default payment timeline for stage paymentsColumn chart. Payment due: 7 days; Latest pay less notice: 17 days; Final date for payment: 24 days.0 days10 days20 days30 daysPayment due: 7 days7 daysPaymentdueLatest pay less notice: 17 days17 daysLatest paylessnoticeFinal date for payment: 24 days24 daysFinal dateforpayment

Source: legislation.gov.uk (The National Archives), 1998[2]

Show the data
MilestoneDays after period ends
Payment due7 days
Latest pay less notice17 days
Final date for payment24 days

In other words, under the default rules a valuation at the end of a month would be paid about three and a half weeks later. Some main contractors' standard terms are longer, which is lawful if the contract states it and meets the Act's other requirements. That is why the dates are worth negotiating.

Rights the contract cannot take away

  • Stage payments: you can claim payment by instalments unless the contract says the work will take less than 45 days[1].
  • No pay-when-paid: a clause making your payment conditional on the main contractor being paid by the client is ineffective, unless that client is insolvent[1].
  • Suspension: if a sum due is not paid by the final date and no valid pay less notice was given, you can suspend performance after giving at least seven days' notice of your intention and the grounds[1]. The party in default must then pay your reasonable costs and expenses of suspending.
  • Adjudication: you can refer a dispute to adjudication, a fast route to a binding decision; see Construction Act payment rules and adjudication.

These rights apply to construction contracts. Most work for homeowners in their own homes is excluded from the Act, so domestic customers are handled differently.

What to negotiate before you sign

  1. A clear valuation date each month and the format of your application.
  2. The shortest payment period you can get between due date and final date; ask for the Scheme periods as a starting point.
  3. Who issues the payment notice and when, and what happens if it does not arrive.
  4. Retention: percentage, release triggers and whether a retention bond can replace it.
  5. Set-off: limits on deducting sums for other contracts or disputed claims.
  6. CIS: confirmation of your status and that deductions apply to labour only.
  7. Materials on site: whether you can be paid for materials delivered but not yet fixed.
  8. Variations: how instructions are given and how they are valued, in writing.

On developer work, payment terms interact with plot stages and retentions; see working for housebuilders. For how much contract work your firm should carry at all, see balancing domestic and commercial work.

Red flags in a main contractor's terms

Standard subcontract forms are often amended by main contractors, and the amendments are where the risk sits. Read the schedule of amendments before the main body, and look for these patterns:

  • A long gap between due date and final date, with no reason given.
  • Payment conditional on certificates or approvals that are outside your control.
  • Broad set-off rights allowing the contractor to deduct sums from other contracts or for loosely defined losses.
  • Retention released only on completion of the whole development rather than your package.
  • A requirement to give notice of every claim within a very short period, or lose the right to it.
  • Liquidated damages passed down from the main contract with no cap and no link to your actual delay.
  • An obligation to keep working even when payment is late, which conflicts with your statutory right to suspend.

You will not remove every clause, but you can usually trade. Accept a slightly longer payment period in exchange for a shorter retention period, or agree a cap on set-off. Put every agreed change in writing in the subcontract itself, not in an email that may be forgotten when the site manager changes.

If a clause seems to undermine one of your statutory rights, ask the contractor to explain it before you sign. Where the contract fails to meet the Act's requirements, the Scheme's provisions apply instead, but it is far better to agree clear terms at the start than to argue about them halfway through a project.

Example: a monthly payment timeline

Example: a heating subcontractor's contract follows the Scheme periods. It submits its application for October on 31 October. Payment becomes due on 7 November. The main contractor issues a payment notice on 10 November for a lower sum than applied for, with a breakdown. The final date for payment is 24 November, so any pay less notice must arrive by 17 November. None arrives, so the notified sum is due in full by 24 November. Nothing has arrived by 25 November, so the subcontractor sends a notice of intention to suspend, stating the grounds, and chases the difference between its application and the notice through the next valuation.

Templates you can adapt

Friendly chase before the final date: "Hello, our application for October was submitted on 31 October and your payment notice confirmed the sum due. The final date for payment is 24 November. Please confirm the payment is scheduled. Thank you."

Notice of intention to suspend, sent only after the final date has passed: "We refer to the sum notified as due in your payment notice dated 10 November under subcontract number [number]. That sum was not paid by the final date for payment and no pay less notice was received. In accordance with section 112 of the Housing Grants, Construction and Regeneration Act 1996, we give notice of our intention to suspend performance of our obligations under the subcontract seven days from receipt of this notice, unless payment is made in full before then."

Take advice before suspending on a large contract, and keep a copy of every notice with proof of delivery. Most payers pay once they see a correctly worded notice.

A monthly cash routine for contract work

  1. Diary every date

    For each contract, put the application date, due date, payment notice deadline, pay less deadline and final date in a shared calendar.

  2. Apply on time, every time

    Submit applications in the agreed format with supporting photos and measurements on or before the valuation date.

  3. Check the notice

    When the payment notice arrives, compare it with your application and query differences in writing within days.

  4. Chase before the final date

    A short reminder a few days before the final date prevents most late payments.

  5. Act after the final date

    If payment is late, send a reminder that statutory interest applies, then consider a suspension notice.

Businesses can charge statutory interest of 8% plus the Bank of England base rate on late business-to-business payments[4]. Most plumbing subcontract work also falls under CIS, with 20% deducted for registered subcontractors and 30% for those not registered or verified[6], so build deductions into your cash forecast too. For chasing commercial debts more broadly, see late payment on commercial debts.

Frequently asked questions

What is a pay less notice?

A notice from the payer saying it intends to pay less than the sum in the payment notice, and why. It must be given before the deadline set by the contract or, by default, not later than seven days before the final date for payment.

Can a main contractor pay me only when the client pays them?

Under the Construction Act, a pay-when-paid clause is ineffective in a construction contract unless the client, or a party further up the chain, is insolvent.

How much notice do I need to give before suspending work?

At least seven days' notice of your intention to suspend, stating the grounds. The right arises when a sum due has not been paid by the final date and no valid pay less notice was given.

Do these rules apply to domestic customers?

Contracts with residential occupiers for work on their own homes are excluded from the Construction Act's payment and adjudication rules. Consumer law applies instead.

References

  1. legislation.gov.uk (The National Archives) (1996). Housing Grants, Construction and Regeneration Act 1996, Part II: payment (sections 109 to 113) (opens in a new tab) ↑

  2. legislation.gov.uk (The National Archives) (1998). The Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule Part II: payment (opens in a new tab) ↑

  3. Department for Business and Trade (GOV.UK) (2025). Longitudinal Small Business Survey 2025: SME employers (businesses with 1 to 249 employees) (opens in a new tab) ↑

  4. GOV.UK (2026). Late commercial payments: charging interest (opens in a new tab) ↑

  5. Department for Business and Trade (GOV.UK) (2025). Longitudinal Small Business Survey 2025: SME employers (businesses with 1 to 249 employees) (opens in a new tab) ↑

  6. GOV.UK (2026). What you must do as a CIS subcontractor: get paid (opens in a new tab) ↑

Book a demo

See Ava handle your calls.

Book a short demo. We’ll walk through your calls and workflow, and agree what Ava should take care of.

Book a demo