Key takeaways
- On business-to-business debts you can claim statutory interest of 8% plus the Bank of England base rate[1].
- You can also add fixed compensation of £40, £70 or £100 per invoice, depending on its size[2].
- If no payment date was agreed, a business payment is late 30 days after the invoice or the work, whichever is later[2].
- The base rate used is the one in force on 30 June or 31 December before the interest starts to run[3].
- Use the right to interest mainly as leverage; mention it in your terms and your reminders, then decide case by case.
Who this applies to
The Late Payment of Commercial Debts (Interest) Act 1998 gives businesses a legal right to interest and compensation when another business pays late. For a plumbing or heating firm that covers most commercial work: letting agents and landlords who trade as businesses, managing agents, facilities management companies, builders, developers, schools and offices. It does not cover domestic customers paying for work on their own homes.
Construction businesses need it more than most. In 2025, 45% of construction SME employers named late payment as a major obstacle, the highest of any sector[4], and late payment was a problem for 63% of SME employers that gave trade credit[5].
When a business payment becomes late
If you agree a payment date, it must usually be within 30 days for public authorities or 60 days for business transactions. A longer period can be agreed between businesses, but it must be fair to both[2]. If you do not agree a payment date, the law says the payment is late 30 days after the customer gets the invoice, or after you deliver the goods or provide the service if that is later[2].
Put a payment period on every commercial quote and invoice, for example '30 days from the date of invoice'. Without it you fall back on the default, and arguments about when the invoice was received become harder to win.
Statutory interest: the rate
Statutory interest is 8% a year plus the Bank of England base rate for business-to-business transactions[1]. You cannot claim it if your contract sets a different interest rate, and you cannot use a lower rate in a contract with a public authority[1].
The base rate part is fixed at a reference date. Under the 2002 rate order, the rate is 8% over the official dealing rate in force on 30 June for interest that starts to run between 1 July and 31 December, or on 31 December for interest that starts to run between 1 January and 30 June[3]. Bank Rate was raised to 4% on 5 November 2026[6], but a debt that became late in November 2026 still uses the rate in force on 30 June 2026. Check the Bank of England's rate history for the right date.
Fixed compensation per invoice
On top of interest, you can charge a fixed sum for the cost of recovering each late payment. You can only charge it once per payment, and the amount depends on the size of the debt[2]. You can also claim reasonable costs each time you try to recover the debt[2].
Source: GOV.UK, 2026[2]
Show the data
| Item | Value |
|---|---|
| Debt up to £999.99 | £40 |
| £1,000 to £9,999.99 | £70 |
| £10,000 or more | £100 |
Working out a claim
Find the date the payment became late
The agreed due date, or 30 days after the invoice or the work if nothing was agreed.
Find the reference rate
The base rate on 30 June or 31 December before that date. Add 8% to get the annual rate.[3]
Work out the annual interest
Multiply the debt by the annual rate.
Turn it into daily interest
Divide by 365 and multiply by the number of days late. GOV.UK's own example uses this method[1].
Add the fixed sum
£40, £70 or £100 depending on the size of the debt.[2]
Send a new invoice
GOV.UK says to send a new invoice if you decide to add interest to the money you are owed[1].
Example (fictional): a letting agent owes £4,800 for a boiler replacement in a rented flat. It pays 45 days late. Assuming a reference rate of 4%, statutory interest is 12% a year, so £576 a year, or about £1.58 a day. Forty-five days comes to about £71. The debt is between £1,000 and £9,999.99, so the fixed sum is £70. The firm could add about £141 to the debt.
Should you actually charge it?
Claiming interest is a right, not a duty. Many small firms never use it because they fear losing the customer. The practical answer is to use it deliberately.
| Situation | Suggested approach |
|---|---|
| Good customer, first late payment | Friendly reminder; mention your terms, do not add interest yet |
| Regular customer who always pays late | Add the fixed sum and interest on the next late invoice, as your terms say |
| Customer who has stopped responding | Final notice including interest and compensation, then a letter before action |
| Large contractor using you as a bank | Add interest routinely and review whether the work is worth it |
| Public body | Check the contract terms; payment periods are usually shorter |
Mentioning interest in your terms and early reminders often does the work on its own. Accounts departments prioritise suppliers who are clear about their rights.
Wording for terms and reminders
- On quotes and invoices: 'Payment is due within 30 days of the invoice date. We reserve the right to claim interest and compensation under the Late Payment of Commercial Debts (Interest) Act 1998.'
- First reminder: 'Invoice 2217 was due on 3 March. Please arrange payment this week. Thank you.'
- Second reminder: 'Invoice 2217 is now 21 days overdue. Unless we receive payment by 31 March, we will add statutory interest and fixed compensation as set out in our terms.'
- Revised invoice: list the original amount, the interest calculation with dates and rate, and the fixed sum, each on its own line.
Mistakes that weaken a claim
- No payment period on the quote or invoice, so the due date is open to argument.
- Invoices sent to the wrong person or without the customer's order number, giving the accounts team a reason to sit on them.
- Adding interest at a rate you made up rather than the statutory rate or the rate in your contract.
- Charging the fixed sum more than once for the same invoice. It can only be charged once per payment.
- Threatening interest and then never following through, which teaches slow payers that your terms are optional.
- Waiting months before the first reminder. The longer an invoice is overdue, the harder it is to collect.
If the customer still does not pay
Interest and compensation do not collect themselves. If a business ignores your final notice, the next step is a formal letter before action setting out the debt, the interest, the fixed sum and a deadline, and saying you will start court proceedings if it is not paid. Many debts are paid at this stage.
If not, weigh the amount against the time and cost of a claim. For smaller debts the online money claim route is designed to be used without a solicitor. For larger or disputed debts, or where a main contractor raises counterclaims, take advice early. Keep your paperwork in order throughout: the order, the signed job sheet, the invoice, the reminders and your interest calculation.
Bigger construction contracts
On larger jobs for main contractors, construction contract law adds its own payment rules, including payment notices, pay less notices and limits on pay-when-paid clauses. Our guide to retentions on construction jobs explains how retentions interact with those rules, and cash flow for plumbing firms shows how to plan around slow commercial payers.
Whatever the contract, keep evidence: the order or instruction, the job sheet signed on completion, the invoice and proof of when it was sent. If you ever have to go to court, those documents decide the outcome.
Example: using the right without losing the customer
Example (fictional): a heating firm in Bristol services boilers for a property management company that routinely pays at 70 days against agreed 30-day terms. The firm adds the late payment wording to every invoice and, after the next late payment, sends a revised invoice with the fixed sum and interest, explaining politely that this is now its standard practice.
Example: the managing agent's accounts team moves the firm onto its faster payment run. Over the following six months invoices are paid in about 35 days, and the firm stops having to chase. It never actually collects much interest; the point was to be taken seriously.
Frequently asked questions
Can I charge late payment interest to a homeowner?
Not under the Late Payment of Commercial Debts Act, which only covers business-to-business debts. You can only charge consumers interest if it was clearly agreed in your terms beforehand.
What is the statutory interest rate on late invoices?
8% a year plus the Bank of England base rate in force on the reference date: 30 June or 31 December before the interest starts to run.
How much compensation can I add to a late invoice?
£40 for debts up to £999.99, £70 for £1,000 to £9,999.99 and £100 for £10,000 or more, once per invoice.
Do I need to have it in my terms to claim interest?
No, the right exists by law for business debts unless your contract sets a different rate. Stating it in your terms makes customers aware and makes the claim easier.
References
GOV.UK (2026). Late commercial payments: charging interest (opens in a new tab) ↑
GOV.UK (2026). Late commercial payments: charging interest and debt recovery (full guide) (opens in a new tab) ↑
legislation.gov.uk (The National Archives) (2002). The Late Payment of Commercial Debts (Rate of Interest) (No. 3) Order 2002, article 4 (opens in a new tab) ↑
Department for Business and Trade (GOV.UK) (2025). Longitudinal Small Business Survey 2025: SME employers (businesses with 1 to 249 employees) (opens in a new tab) ↑
Department for Business and Trade (GOV.UK) (2025). Longitudinal Small Business Survey 2025: SME employers (businesses with 1 to 249 employees) (opens in a new tab) ↑
Bank of England (2026). Interest rates and Bank Rate (opens in a new tab) ↑