Key takeaways
- Contracts with a residential occupier for work on their own home are outside Part II of the Construction Act[1].
- Your subcontract with a builder doing a homeowner's extension is still covered, because you are not contracting with the occupier.
- Either party to a construction contract can refer a dispute to adjudication; referral follows within 7 days of the notice and the decision is due within 28 days[2].
- The 28 days can be extended by up to 14 days with the referring party's consent, or longer if both agree[2].
- Adjudication suits clear payment disputes; get the paperwork in order before you start one.
What the Construction Act does for subcontractors
Part II of the Housing Grants, Construction and Regeneration Act 1996 sets minimum rules for construction contracts in England, Wales and Scotland, with parallel legislation in Northern Ireland. It does two things that matter to plumbing and heating firms. It sets out how payment must work, and it gives each party a right to take a dispute to adjudication, a fast process that produces a binding decision in weeks rather than the months or years a court case can take.
Since 2011, in England and Wales, these rules have applied to oral and partly written contracts as well as written ones, so a subcontract agreed by phone and email can still be covered. What matters is whether the work counts as construction operations and whether an exclusion applies.
Why most homeowner work is excluded
The Act does not apply to a construction contract with a residential occupier[1]. That means a contract which principally relates to operations on a dwelling that one of the parties occupies, or intends to occupy, as their residence[1]. When a homeowner books you to replace their boiler or refit their bathroom, the Act's payment and adjudication rules do not apply to that contract. Consumer law governs it instead.
| Scenario | Is your contract covered by Part II? | Why |
|---|---|---|
| Homeowner hires you to replace the boiler in the house they live in | No | Contract with a residential occupier |
| Homeowner buying a house hires you to refit it before moving in | No | They intend to occupy it as their residence |
| Builder hires you to do the plumbing on a homeowner's extension | Yes, for your subcontract with the builder | You contract with the builder, not the occupier |
| Private landlord hires you to replace heating in a let flat | Usually yes | The landlord does not live there |
| Housing association or council repair contract | Usually yes | Not a residential occupier contract |
| Main contractor subcontracts heating on a new-build site | Yes | Standard construction subcontract |
The exclusion protects homeowners from adjudication. It does not protect the builder who employs you on a homeowner's project; your subcontract with that builder keeps its statutory rights.
Payment rules in brief
Covered contracts must provide an adequate mechanism for working out what is due and when. The Act gives an entitlement to stage payments for work expected to last 45 days or more, requires a payment notice within five days of each due date, sets out how a payer may give a pay less notice, makes pay-when-paid clauses ineffective except on insolvency and allows suspension for non-payment on seven days' notice[3].
Those rules are the foundation of most adjudications brought by subcontractors. Our guide to payment terms with main contractors explains how to negotiate and run them month by month. The underlying problem is common: 45% of construction SME employers named late payment as a major obstacle in 2025[4].
How adjudication works
A party to a construction contract has the right to refer a dispute arising under the contract to adjudication[2]. The contract must let either party give notice of its intention to refer a dispute at any time, and must provide a timetable to appoint the adjudicator and refer the dispute within 7 days of that notice[2]. The adjudicator must reach a decision within 28 days of referral, or a longer period the parties agree; the adjudicator can extend the 28 days by up to 14 days with the consent of the party that referred the dispute[2].
Source: legislation.gov.uk (The National Archives), 1996[2]
Show the data
| Step | Days |
|---|---|
| Referral after notice | 7 days |
| Decision after referral | 28 days |
| Decision if extended by referring party | 42 days |
The decision is binding until the dispute is finally settled by agreement, arbitration or the courts, and the courts generally enforce adjudicators' decisions quickly. In practice most parties accept the decision and move on. If the contract does not contain compliant adjudication terms, the Scheme for Construction Contracts supplies them.
Running an adjudication: the sequence
Define the dispute
Be precise: for example, the sum notified as due on a specific payment notice that was not paid by the final date. Vague or shifting disputes cause jurisdiction challenges.
Send the notice of adjudication
State the parties, the contract, the dispute and the decision you want. This starts the timetable.
Appoint the adjudicator
Use the person or nominating body named in the contract. If none is named, apply to an adjudicator nominating body.
Serve the referral within 7 days
Send the referral notice with your evidence: contract, applications, payment notices, correspondence, photographs and a clear calculation.
Respond to the other side
The adjudicator sets a timetable for the response and any reply. Keep submissions short and tied to documents.
Receive the decision
The decision normally arrives within 28 days of referral, unless extended. Comply with it, or enforce it if the other side does not pay.
Records that win adjudications
Adjudicators decide on documents, under time pressure. The party with a clear, complete paper trail usually has the advantage, and that trail has to be built during the job, not in the week the dispute starts.
- The signed subcontract, every amendment and the schedule of rates.
- Each payment application, with the date and method of submission.
- Every payment notice and pay less notice received, with the date received.
- Written instructions for variations, even short emails or site instruction sheets.
- Daily site records: who worked where, what was completed and any delays caused by others.
- Dated photographs of completed work before it was covered or handed over.
- Correspondence about defects, and evidence of when each was put right.
Store everything for each contract in one folder, named and dated consistently, so that a referral can be assembled in a day. Many small firms lose strong claims simply because they cannot prove when an application was sent or what was agreed on site.
Also keep a short timeline document for each contract, updated monthly: applications, notices, payments and key events. It becomes the backbone of a referral if you ever need one, and in most cases simply having it makes negotiation easier because you can quote dates with confidence.
Notified sum and true value
Many subcontractor adjudications are about the notified sum: the payer missed the payment notice or pay less notice deadline, so the sum in your application or its notice became due in full. These are sometimes called smash-and-grab claims. They are quick because they turn on dates and documents rather than on measurement of work.
The payer is not left without a remedy. It can bring its own adjudication on the true value of the work, but the courts have held that it must usually pay the notified sum first. For a small subcontractor the lesson runs both ways: get your own applications and notices right, because a missed deadline can cost you as easily as it can help you.
Example: a disputed valuation
Example: a heating subcontractor applies for the final account on a block of flats. The main contractor's payment notice values the work at much less, citing defects but listing none, and no pay less notice follows. After the final date passes, the subcontractor sends a notice of adjudication claiming the notified sum, nominates an adjudicator through the body named in the subcontract and serves its referral five days later with every application, notice and email in date order. The main contractor pays the notified sum before the decision is due and raises its defects claim separately, which the parties settle by agreement a month later.
When adjudication makes sense, and when it does not
- Strong case: a clear sum, clear dates and missed notices, or a simple valuation dispute with good records.
- Think again: complex delay and defects claims with poor records, where costs can run high and each side usually bears its own.
- Consider the relationship: adjudicating against your main source of work may end it, so try a direct, documented negotiation first.
- Check the amount: for small sums, a firm letter and a statutory interest claim may get the money faster.
On business debts you can also claim statutory interest of 8% plus the Bank of England base rate[5]. That right covers business-to-business contracts only. Late payment was a problem for 63% of UK SME employers that gave trade credit in 2025[6], so build your chasing routine before you need a formal process.
For domestic disputes
Because homeowner contracts are excluded, disputes with domestic customers go through a different route: your own complaints process, a trade association or alternative dispute resolution scheme if you belong to one, and the small claims track of the county court for unpaid invoices. Clear written quotes, signed acceptance and photographs matter even more there. See disputes over damage for the domestic side, and working for housebuilders for how these rules shape developer subcontracts.
Frequently asked questions
Can I take a homeowner to adjudication?
Not under the Construction Act if the contract is with a residential occupier for work on their own home. Use your complaints process, any ADR scheme you belong to or the small claims court instead.
How long does construction adjudication take?
The referral follows within 7 days of the notice of adjudication, and the decision is due within 28 days of referral, extendable by up to 14 days with the referring party's consent or longer if both agree.
Is an adjudicator's decision final?
It is binding until the dispute is finally decided by agreement, arbitration or the courts. Courts generally enforce adjudication decisions promptly.
Do I need a solicitor for adjudication?
Not necessarily for a simple notified sum claim with clear documents, but advice is wise for larger or complex disputes. Each party usually bears its own costs.
References
legislation.gov.uk (The National Archives) (1996). Housing Grants, Construction and Regeneration Act 1996, section 106: residential occupiers (opens in a new tab) ↑
legislation.gov.uk (The National Archives) (1996). Housing Grants, Construction and Regeneration Act 1996, section 108: right to refer disputes to adjudication (opens in a new tab) ↑
legislation.gov.uk (The National Archives) (1996). Housing Grants, Construction and Regeneration Act 1996, Part II: payment (sections 109 to 113) (opens in a new tab) ↑
Department for Business and Trade (GOV.UK) (2025). Longitudinal Small Business Survey 2025: SME employers (businesses with 1 to 249 employees) (opens in a new tab) ↑
GOV.UK (2026). Late commercial payments: charging interest (opens in a new tab) ↑
Department for Business and Trade (GOV.UK) (2025). Longitudinal Small Business Survey 2025: SME employers (businesses with 1 to 249 employees) (opens in a new tab) ↑