Key takeaways
- Since 29 May 2025, permitted development in England allows units within 1m of the boundary, up to 1.5m³ on houses and two units on detached houses[1][2].
- Every air source heat pump installed under permitted development must comply with the MCS sound calculation and noise limit, MCS 020 a[2].
- Listed buildings, pitched roofs, scheduled monuments and some walls fronting highways still fall outside permitted development[1].
- Do the noise calculation at survey, site the unit to minimise its effect on neighbours and keep the record.
Most installs no longer need a planning application
Planning used to be a regular reason for heat pump jobs stalling. The permitted development right for air source heat pumps in England was amended to give more flexibility, so that more households, particularly those with less outdoor space, can install one without a planning application[2]. Government says the changes were informed by an independent review of noise emissions and guidance, which indicated that heat pumps are generally quiet and noise complaints are rare[2]. One installer, Aira, reported that the share of its customers needing a planning application fell from 30-40% to 5-10% after the update[2].
That makes the installer's survey more important, not less. Under permitted development nobody from the council checks the position before work starts. You are the one deciding whether the installation meets the conditions, so the checks need to be done properly and recorded.
What changed in 2025
The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2025 changed Class G of Part 14 from 29 May 2025[1]. The changes allow heat pumps to be installed within 1m of the property boundary, raise the size limit for the outdoor unit from 0.6m³ to 1.5m³ for houses, double the number permitted on detached houses from one to two, and allow units that can also cool, which brings air-to-air heat pumps into the right[2]. A unit used solely for cooling is not covered[1].
Source: Department for Energy Security and Net Zero (GOV.UK), 2026[2]
Show the data
| Item | Value |
|---|---|
| Before the 2025 change | 0.6 m³ |
| From 29 May 2025 | 1.5 m³ |
The Class G checks
| Check | England rule under Class G | Record |
|---|---|---|
| Number of units | One on a house that is not detached or on a block of flats; two on a detached house | Property type and units proposed |
| Size | Outdoor unit, including housing, no more than 1.5m³ on a house or 0.6m³ on a block of flats | Model and dimensions |
| Roofs | Not on a pitched roof; not within 1m of the edge of a flat roof | Mounting position |
| Protected sites | Not on a scheduled monument or a listed building or its curtilage | Listing check result |
| Conservation areas and World Heritage Sites | Not on a wall or roof fronting a highway, or nearer a bounding highway than the house | Elevation and highway position |
| Other land | Not on a wall fronting a highway above ground floor level | Wall and height |
| Noise | Must comply with the MCS Planning Standards | MCS 020 a calculation |
Development is also subject to conditions: the unit must, so far as practicable, be sited to minimise its effect on the external appearance of the building and on the amenity of the area, and it must be removed as soon as reasonably practicable when no longer needed[1].
Noise: the MCS 020 a calculation
Class G only applies if the heat pump complies with the MCS Planning Standards[1], and government states that every air source heat pump installed under permitted development must comply with the MCS sound calculation and noise limit, MCS 020 a[2]. Treat the calculation as part of the design, not a form filled in after the unit is fixed to the wall.
Find the assessment position
Identify the nearest habitable room window or door of a neighbouring property that the method requires you to assess.
Measure the distance
Measure from the unit position to the assessment position, as the method specifies.
Count reflective surfaces
Note walls and ground surfaces near the unit, which raise the sound level the method assumes.
Check for barriers
Record any solid barrier between the unit and the assessment position, and whether it blocks the line of sight.
Use the manufacturer's sound data
Take the sound power level for the model and mode from the manufacturer's published data.
Compare with the limit
Complete the calculation in the current MCS 020 a version and compare the result with its limit; if it fails, move the unit or choose a quieter model.
Siting for appearance and amenity
Passing the noise calculation is the minimum. The condition to minimise the effect on appearance and amenity[1] is a reason to think about where the unit is seen and heard from, not just where it fits. Customers are also more relaxed about a unit they cannot see from the street or the patio.
- Prefer side or rear elevations away from neighbours' bedroom windows and seating areas.
- Keep away from corners and enclosed spaces where reflections raise noise.
- Leave the airflow clearances the manufacturer requires, or efficiency and noise both suffer.
- Use anti-vibration mounts and a firm base, and keep pipe runs tidy and insulated.
- Think about defrost water and where it will drain or freeze.
What customers ask about noise
Customers worry about two things: whether the unit will annoy them, and whether it will annoy the neighbours. Answer both with facts about the specific model and position rather than general reassurance. Explain that the unit is quietest in mild weather and works harder on the coldest days, that a defrost cycle sounds different from normal running, and that a well-chosen position, a solid base and anti-vibration mounts make a noticeable difference.
If you have installed the same model nearby, offer to show the customer one running. Hearing a unit in a real garden settles more doubts than any data sheet, and it gives you a chance to show the siting and finish you aim for.
When planning permission is still needed
Some installations fall outside Class G and need a planning application: listed buildings and land within their curtilage, scheduled monuments, pitched roofs, units larger than the volume limit, more units than the limit, and certain positions in conservation areas or on walls fronting a highway[1]. Flats have tighter size limits, and leaseholders may also need the freeholder's consent, which is separate from planning.
Where you are unsure, the customer can ask the local planning authority for a lawful development certificate before work starts. It costs time, but it is far cheaper than removing a unit after a complaint. Build the possibility into your programme: if a job needs a planning application, tell the customer at survey, explain what the application involves and agree whether you will prepare the drawings and noise information or they will.
Example: a semi with a narrow side passage
Example (fictional): a semi-detached house has a side passage about 1.2m wide, with the neighbour's kitchen window opposite. Before 2025 the boundary rule would have ruled the passage out. The installer checks Class G, confirms one unit within the volume limit is allowed on a semi, and runs the MCS 020 a calculation for the passage position. The reflective walls on both sides push the result over the limit.
The installer then checks the rear elevation, which has one reflective wall, a greater distance to the neighbour's nearest window and a garden fence that blocks the line of sight. The calculation passes there. The customer accepts a slightly longer pipe run, and the record shows both calculations and why the rear was chosen.
Talking to the neighbours
Permitted development does not require you to consult neighbours, but a short conversation often prevents a complaint. Suggest the customer tells the neighbour where the unit will go, roughly what it sounds like and that it has passed the noise check. If a complaint arrives later, your calculation, photos and siting notes let you answer it with evidence. Every service you supply must be carried out with reasonable care and skill[3], and a careful siting record is part of showing that.
With almost 100,000 hydronic heat pumps sold in the UK in 2024[4], neighbours are increasingly used to seeing them. The installs that cause friction are the ones squeezed into the worst spot to save a few metres of pipe.
Records to keep for every permitted development install
- The Class G checklist completed for the property, with the property type and number of units.
- The model, its outdoor unit dimensions and the calculated volume.
- Listed building and conservation area checks, with the source and date.
- The MCS 020 a calculation, with photos of the assessment position, distances and reflective surfaces.
- Photos of the finished installation from the street, the garden and the neighbour's side where visible.
- Any alternative positions considered and why they were rejected.
Keep the file with the commissioning records for the life of the installation. If the council, a neighbour or a future buyer's solicitor asks whether the unit was installed under permitted development, this file is the answer.
Frequently asked questions
Do heat pumps still need to be 1m from the boundary in England?
No. Since the 2025 amendment, permitted development allows air source heat pumps within 1m of the property boundary, subject to the other conditions.
Can I install two heat pumps under permitted development?
On a detached house, yes. On other houses and blocks of flats the limit is one.
Is the MCS noise check still required?
Yes. Units installed under permitted development must comply with the MCS sound calculation and noise limit, MCS 020 a.
Does a listed building need planning for a heat pump?
Yes. Class G does not apply to listed buildings or land within their curtilage, so a planning application and usually listed building consent are needed.
References
legislation.gov.uk (The National Archives) (2025). The Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2, Part 14 (opens in a new tab) ↑
Department for Energy Security and Net Zero (GOV.UK) (2026). Warm Homes Plan (opens in a new tab) ↑
legislation.gov.uk (The National Archives) (2015). Consumer Rights Act 2015, section 49 (opens in a new tab) ↑
Heating and Hotwater Industry Council (HHIC) (2024). Bumper year for UK heat pumps (opens in a new tab) ↑