Gas tightness testing: the IGEM/UP/1B Edition 4 update

IGEM/UP/1B Edition 4 is effective from 1 October 2026: scope, permissible loss and installation volume, the new purge volume rule and updating your forms.

Ava research teamPublished 7 min read

On this page
  1. The dates that matter
  2. What is in scope
  3. What IGEM highlights for engineers
  4. Reading a pressure loss: the decision path
  5. Why the same leak rate gives different readings
  6. When no loss is acceptable at all
  7. When a test fails: explaining it to the customer
  8. Updating procedures and paperwork
  9. A short implementation plan
  10. Worked example
  11. Frequently asked questions
  12. References

Key takeaways

  • IGEM/UP/1B Edition 4 was published in March 2026 and became effective on 1 October 2026; Edition 3 was withdrawn on 30 September 2026.
  • Permissible pressure loss is now assessed against the installation volume and the fuel gas, and pipework itself must show no perceptible loss.
  • Installation volume must be calculated before every purge, and purge volume is 1.5 times installation volume.
  • Where appliances cannot be isolated, or the pipework and appliances are new, no pressure loss is permitted.
  • Update job sheets, software templates and briefings now; any test since 1 October 2026 should follow Edition 4.

The dates that matter

IGEM/UP/1B covers tightness testing and direct purging of small natural gas, LPG and LPG/Air installations, which is most of the domestic and small commercial work a heating engineer does. Edition 4 was published in March 2026 and supersedes Edition 3[1]. IGEM expected operatives to adopt the new procedures as soon as reasonably practicable, and in all circumstances Edition 4 became effective from 1 October 2026; Edition 3 remained available until it was withdrawn on 30 September 2026[1].

If your engineers, forms or software still follow Edition 3, any tightness test or purge carried out since 1 October 2026 was done to a withdrawn standard. Fix the procedure first, then the paperwork.

Standards are not law in themselves, but they are how competence is judged. The law requires anyone working on a gas fitting to be competent[2], and HSE's code of practice says that knowledge must be kept up to date with changes in the law, technology and safe working practice[3]. Working to a withdrawn edition is hard to defend as competent practice.

What is in scope

Edition 4 applies to sections of installation pipework, including meters, within set limits. IGE/UP/1 applies to installations with volumes above the limit, and IGEM/UP/1C covers meter installations within its own scope[1]. Edition 4 also covers caravans and leisure accommodation vehicles[1].

Scope limits of IGEM/UP/1B Edition 4, as published by IGEM
ParameterLimit in Edition 4
Maximum operating pressure at the emergency control valve outlet (NG and LPG/Air)Not exceeding 2 bar
Nominal bore of pipeworkNot exceeding 35 mm (DN32, R1¼)
Meter badged capacityNot exceeding 16 m3/h
Installation volume (individual dwelling or non-domestic premises)Not exceeding 0.035 m3
Nominal operating pressure, NG and LPG/AirNot exceeding 21 mbar
Nominal operating pressure, LPG at final stage regulator outletNot exceeding 37 mbar

For anything outside those limits, choose the right standard before you start. IGEM's own selection figure in the standard helps with borderline cases.

What IGEM highlights for engineers

IGEM's published FAQ on Edition 4 focuses on a few points that change day-to-day practice[4]:

  • Permissible pressure loss is defined in the standard and is based on the installation volume and the fuel gas; those limits apply wherever a pressure loss has to be assessed.
  • The purging procedure itself is unchanged, but the method for working out purge volume has been revised for some installations.
  • For all purging, installation volume must be calculated, and purge volume is determined as 1.5 times the installation volume.
  • That applies even where the tightness test itself did not need the installation volume: it still has to be calculated before purging.
  • When testing the installation pipework alone, the test includes the meter, unless it is carried out from an additional emergency control valve.

Reading a pressure loss: the decision path

  1. Look for perceptible movement

    If there is perceptible movement, the engineer must investigate whether the loss is on the installation pipework or on the appliances[4].

  2. Pipework first

    A perceptible pressure loss on pipework is a failure and must be repaired or made safe. There are no permissible leakage limits when proving installation pipework gas tight[4].

  3. Appliances connected, loss found

    Where existing appliances are connected and a loss is found, isolate the appliances and confirm there is no loss on the pipework and meter[4].

  4. Compare with the smallest limit

    If the loss is below the smallest permissible limit for that gas, it can be accepted without calculating installation volume for the comparison[4].

  5. Above the smallest limit

    Calculate the installation volume and confirm the loss is within the relevant table in the standard for natural gas or LPG. If it exceeds the limit, or there is a smell of gas, the test has failed and remedial action is required[4].

Why the same leak rate gives different readings

Engineers sometimes ask why 1 mbar might be the limit on one job and 8 mbar on another. IGEM's answer is that the maximum permissible pressure loss is based on a leakage rate of 19 ml per minute for the installation volume: an 8 mbar loss on a small installation volume is roughly equivalent to a 1 mbar loss on a larger one, and both fall within the same leakage limit[4].

Two readings, one leakage limit: IGEM's Edition 4 exampleBoth correspond roughly to the 19 ml per minute leakage basis in IGEM's FAQ
Two readings, one leakage limit: IGEM's Edition 4 exampleComparison. Smaller installation volume: 8 mbar; Larger installation volume: 1 mbar.8 mbarSmaller installation volumeSmaller installation volume: 8 mbar1 mbarLarger installation volumeLarger installation volume: 1 mbarTwo readings, one leakage limit: IGEM's Edition 4 exampleComparison. Smaller installation volume: 8 mbar; Larger installation volume: 1 mbar.8 mbarSmaller installation volumeSmaller installation volume: 8 mbar1 mbarLarger installation volumeLarger installation volume: 1 mbar

Source: Institution of Gas Engineers and Managers (IGEM), 2026[4]

Show the data
ItemValue
Smaller installation volume8 mbar
Larger installation volume1 mbar

That is why calculating installation volume properly matters. An engineer who guesses volume can pass an installation that should fail, or fail one that is acceptable.

When no loss is acceptable at all

IGEM's examples set out situations where no permissible pressure loss is allowed: new pipework with new appliances, and installations where existing appliances are connected because isolating them is not reasonably practicable[4]. In those cases the test must show no perceptible movement.

Make this explicit in your procedures and on your job sheet, because it is the situation where habits from older practice are most likely to creep in.

When a test fails: explaining it to the customer

A failed tightness test is unwelcome news, often delivered on a cold day when the customer expected a routine service. Clear, calm wording helps them accept that the supply has to stay off until the fault is found and fixed.

Script: 'The test shows gas is escaping somewhere in the pipework. I can't leave the supply on while that's the case, so I've turned it off at the meter and labelled it. Next I need to find the leak; most are at joints or fittings and can be repaired today or tomorrow. I'll write down what I found and what happens next.'

  • Make the installation safe first, then explain. Do not debate the result with the supply on.
  • Give the customer the paperwork the unsafe situations procedure requires, and keep a copy.
  • If you cannot trace or make safe an escape, or it is upstream of the emergency control valve, call the gas emergency service. When told of an escape, the gas conveyor must attend as soon as reasonably practicable and stop the escape within 12 hours[5].
  • Record the readings, installation volume, the limit applied and the result, so the next engineer can follow your reasoning.

Customers who understand why the gas is off are less likely to call another firm to 'just turn it back on', which is the outcome that worries engineers most.

Updating procedures and paperwork

  • Buy the standard and its free amendments document from IGEM, and keep a copy where every engineer can read it.
  • Update tightness test and purge forms so they record gas type, installation volume, the permissible limit used, purge volume, gauge type, readings and result.
  • Update any software templates, including certificate apps, and remove old paper forms from vans.
  • Brief every engineer, record attendance and test understanding with two or three worked scenarios.
  • Sample-check completed tests from the last month against the new forms.
  • Check commissioning paperwork too; the paper Benchmark checklist is no longer maintained and the record has moved online and to the Benchmark apps[6].

A short implementation plan

  1. This week: stop old forms

    Withdraw Edition 3 forms and templates from use and tell every engineer in writing.

  2. This week: brief the team

    Thirty minutes on scope, installation volume, purge volume and the no-loss situations.

  3. Within a fortnight: update software

    Confirm your certificate and job sheet tools have Edition 4 fields; ask suppliers for their update dates.

  4. Within a month: audit

    Review a sample of tests by each engineer since 1 October 2026 and correct any procedural gaps.

  5. Ongoing: keep evidence

    File the briefing record, the audit and any corrections, ready for an inspection.

Worked example

Example: a fictional six-engineer firm discovers in November that two engineers' certificate apps still show the old test layout. The office withdraws paper forms the same day, holds a briefing on the purge volume rule and the no-loss situations, and asks the software supplier for the update. An audit of 30 tests done since October finds four where installation volume was not recorded before a purge; the engineers revisit the records with the customers' agreement, and the firm adds a mandatory volume field to its job sheet.

For how inspectors will look at this, see preparing for a Gas Safe inspection. For the landlord paperwork that often sits alongside these tests, see landlord gas safety records, and for keeping qualifications aligned, see planning ACS reassessments.

Frequently asked questions

When did IGEM/UP/1B Edition 4 come into effect?

It was published in March 2026 and became effective from 1 October 2026. Edition 3 was withdrawn on 30 September 2026.

Do I have to calculate installation volume for every tightness test?

Not always for the test itself: if the pressure loss is below the smallest permissible limit for that gas, you can accept it without calculating volume. But installation volume must be calculated before any purge, to work out purge volume.

What is the purge volume under Edition 4?

IGEM's FAQ says purge volume is determined as 1.5 times the installation volume, for all purging.

Is any pressure loss acceptable on pipework?

No. A perceptible pressure loss on installation pipework is a failure that must be repaired or made safe. Permissible limits apply only to the whole installation with existing appliances connected, in the situations the standard describes.

References

  1. Institution of Gas Engineers and Managers (IGEM) (2026). IGEM/UP/1B Edition 4: Tightness testing and direct purging of small LPG/Air, NG and LPG installations (opens in a new tab) ↑

  2. legislation.gov.uk (The National Archives) (1998). The Gas Safety (Installation and Use) Regulations 1998, regulation 3 (opens in a new tab) ↑

  3. Health and Safety Executive (2018). Safety in the installation and use of gas systems and appliances (L56, fifth edition), paragraph 85 (opens in a new tab) ↑

  4. Institution of Gas Engineers and Managers (IGEM) (2026). FAQ: IGEM/UP/1B Edition 4 (opens in a new tab) ↑

  5. legislation.gov.uk (The National Archives) (1996). The Gas Safety (Management) Regulations 1996, regulation 7 (opens in a new tab) ↑

  6. Heating and Hotwater Industry Council (HHIC) (2026). Benchmark goes digital - what homeowners need to know (opens in a new tab) ↑

Book a demo

See Ava handle your calls.

Book a short demo. We’ll walk through your calls and workflow, and agree what Ava should take care of.

Book a demo