Prime cost and provisional sums in plumbing quotes

What prime cost and provisional sums are, when a plumbing or heating quote should use them, how to set honest amounts, and wording customers understand.

Ava research teamPublished 7 min read

On this page
  1. Two allowances that do different jobs
  2. How they compare
  3. When to use each on plumbing and heating work
  4. Setting an honest amount
  5. Talking a customer through the allowances
  6. Worked Example: adjusting the final account
  7. The legal backdrop
  8. Older and rented homes need more of them
  9. Wording that customers understand
  10. Mistakes to avoid
  11. Frequently asked questions
  12. References

Key takeaways

  • A prime cost (PC) sum is an allowance for an item the customer will choose; a provisional sum is an allowance for work that cannot be defined yet.
  • Both are honest tools when the amounts are realistic and the adjustment rule is written down. Both become a trap when set low to win the job.
  • What you say or write about the service can become part of the contract[1], so explain each allowance in plain words.
  • Housing condition varies widely: 22% of private rented homes in England failed the Decent Homes Standard[2], so landlord jobs often need provisional sums.
  • Show the adjustment on the final invoice line by line, with the receipts or measurements behind it.

Two allowances that do different jobs

Quotes for bathrooms, heating upgrades and larger installs often contain figures that are not fixed prices. Used well, these allowances let you give a customer a realistic total before every decision has been made. Used badly, they let a quote look cheaper than the job will be. The difference is in how they are set and how clearly they are explained.

A prime cost sum, often written PC sum, is an amount for supplying an item that has not been chosen yet: a basin, a shower, tiles, a towel rail, sometimes a boiler model. A provisional sum is an amount for work that cannot be fully described at quote stage: repairing a floor you cannot see under, replacing pipework that may or may not be lead, or upgrading a gas supply once you have checked the route. Neither is a guess. Each is your best honest estimate, with a rule for what happens when the real figure is known.

How they compare

Prime cost sums, provisional sums and contingency compared.
FeaturePC sumProvisional sumContingency
What it coversSupply of a named item still to be chosenWork that cannot yet be definedUnknown risks across the whole job
Who decides the final figureThe customer, by choosing the itemThe site, once the work is opened upEvents on the job
LabourUsually priced separately as fixed workIncluded in the sumIncluded
AdjustmentActual cost of the item replaces the allowanceActual work done, valued at agreed ratesOnly spent with approval
Typical plumbing useSanitaryware, taps, showers, tiles, radiatorsFloor repairs, pipe replacement, gas supply upgradeBathrooms and older properties

Keep the three separate on the quote. Mixing them hides the information a customer needs to make decisions and makes the final account harder to explain.

When to use each on plumbing and heating work

  • Bathroom refit where the customer is still choosing products: PC sums for suite, shower, taps and tiles, with fixed labour for fitting.
  • Heating upgrade in an older house: a provisional sum for replacing hidden pipework found when floors are lifted.
  • Boiler relocation: a provisional sum for the gas supply upgrade until you have confirmed the pipe route and length.
  • Landlord refurbishment before a new tenancy: provisional sums for repairs that depend on what is found once the old installation is removed.
  • Kitchen or utility moves: a PC sum for the sink and tap, a provisional sum for altering waste runs through unknown floor voids.

Do not use an allowance for something you could find out with a little more survey time. If lifting one floorboard would tell you whether the pipe is copper or lead, lift it. Allowances are for genuine uncertainty, not for skipping the survey.

Setting an honest amount

  1. Base PC sums on a real product

    Choose a mid-range item that suits the room and the customer's brief, look up the price you would pay, and use that. Name the example product on the quote so the customer can see what the allowance buys.

  2. Base provisional sums on likely work

    Describe the work you expect, estimate it at your normal rates, and say what would make it more or less.

  3. State your handling rule

    Say whether the PC sum is for supply only, whether your handling margin is added to the actual item price, and whether labour changes if the chosen item is harder to fit.

  4. Give a decision date

    Customers must choose PC items by a set date so that ordering does not delay the programme.

  5. Explain the adjustment

    Write how the final figure will be worked out and when the customer will see it.

Low allowances win quotes and lose customers. A bathroom quote with a basin allowance that buys nothing the customer would actually want is a price increase waiting to happen, and customers remember who made it.

Talking a customer through the allowances

Many homeowners have never seen a PC sum before and read any figure that is not fixed as a warning sign. Spend two minutes on it when you hand over the quote, and the allowances become a reason to trust you.

  1. ‘Most of this quote is fixed: the labour, the pipework, the boarding and the finishing. Those figures will not change unless you change the job.’
  2. ‘These lines are allowances for things you are still choosing. I have based each one on a real product so you can see what it buys. Pick something dearer and it goes up; pick something cheaper and it comes down.’
  3. ‘This line is for the floor, which we cannot see until the bath is out. If it is fine, you do not pay it. If it needs work, I will show you before I do anything.’
  4. ‘At the end you will get a sheet showing each allowance, what you actually chose or what we found, and the difference.’

Write the same explanation in a short note at the top of the allowances section of the quote. Customers often share quotes with a partner or a parent, and the note does the explaining when you are not there.

Worked Example: adjusting the final account

Example (fictional): a firm quoted a bathroom with a PC sum of £900 for a shower set and £1,200 for tiles, plus a provisional sum of £400 for floor repairs. The customer chose a shower set at £1,150 and tiles at £1,050. When the old bath came out, two joist ends needed repair, valued at £280 using the rates in the quote.

Example final account adjustments for a fictional bathroom job.
Item (Example)AllowanceActualAdjustment
PC sum: shower set£900£1,150+£250 plus agreed handling margin
PC sum: tiles£1,200£1,050−£150
Provisional sum: floor repairs£400£280−£120

In this Example, the net adjustment is small, and every figure is supported by a receipt or a measured description. The customer sees that the allowances worked in both directions, which is the best possible advertisement for the next job.

Domestic customers are protected by the Consumer Rights Act 2015. Anything said or written to the consumer by or on behalf of the trader about the service can be treated as a term of the contract when the consumer relies on it[1]. If your quote says an allowance ‘should cover a good quality shower’, that sentence matters. Where no price has been agreed, the consumer must pay a reasonable price[3], and every service must be carried out with reasonable care and skill[4].

In practice this means being precise. Say what each allowance covers, how it will be adjusted and that you will ask before spending any provisional sum on work the customer has not seen. Keep the photos and measurements that support each adjustment.

Older and rented homes need more of them

How much uncertainty a job carries depends heavily on the property. In England, 22% of private rented homes failed the Decent Homes Standard, the highest of any tenure, against 10% in the social rented sector[2]. Homes in poor condition are where hidden pipework, damaged floors and botched past repairs turn up.

Homes failing the Decent Homes Standard in England, by tenure, 2024
Homes failing the Decent Homes Standard in England, by tenure, 2024Comparison. Private rented: 22%; Social rented: 10%.22%Private rentedPrivate rented: 22%10%Social rentedSocial rented: 10%Homes failing the Decent Homes Standard in England, by tenure, 2024Comparison. Private rented: 22%; Social rented: 10%.22%Private rentedPrivate rented: 22%10%Social rentedSocial rented: 10%

Source: Ministry of Housing, Communities and Local Government (GOV.UK), 2024[2]

Show the data
ItemValue
Private rented22%
Social rented10%

For landlord work in older stock, a quote built mainly from fixed prices either carries a lot of hidden risk or is priced so high that it loses. A clear set of provisional sums lets the landlord see the likely range and approve the work as it is uncovered.

Wording that customers understand

  • ‘Prime cost allowance for shower set, supply only: £X. Based on a thermostatic bar shower with riser rail, such as [example product]. If you choose a different shower, the difference in our purchase price will be added or credited, plus our handling margin of Y% on any increase.’
  • ‘Provisional sum for floor repairs: £X. We cannot see the floor condition until the bath is removed. We will show you any damage and agree the repair before we start it. Any unused amount is not charged.’
  • ‘Provisional sum for gas supply upgrade: £X. We will confirm the route and pipe size from the meter during first fix and tell you the final figure before any work begins.’

Every allowance needs three things in writing: what it covers, how it is adjusted, and when the customer will be asked to agree the final figure.

Mistakes to avoid

  1. Setting PC sums below the price of anything the customer would realistically choose.
  2. Using a provisional sum for work you could have checked at survey.
  3. Spending a provisional sum without telling the customer first.
  4. Adding handling margin to PC sum increases without having said so in the quote.
  5. Presenting the final account as a single total instead of line by line.

Frequently asked questions

What is the difference between a PC sum and a provisional sum?

A PC sum is an allowance for supplying an item the customer has not chosen yet. A provisional sum is an allowance for work that cannot be defined until the job is opened up.

Can I add a margin to PC sum items?

Yes, if you say so in the quote. State your handling margin and how it applies when the chosen item costs more than the allowance.

Do I have to refund unused provisional sums?

You should not charge for work that was not needed. Say in the quote that any unused amount is not charged, and show the adjustment on the final invoice.

Are allowances binding on me as the trader?

What you say or write about the service can become part of the contract if the customer relies on it[1], so describe each allowance accurately.

References

  1. legislation.gov.uk (The National Archives) (2015). Consumer Rights Act 2015, section 50 (information about the trader or service to be binding) (opens in a new tab) ↑

  2. Ministry of Housing, Communities and Local Government (GOV.UK) (2024). English Housing Survey 2024 to 2025: Chapter 1, housing quality (opens in a new tab) ↑

  3. legislation.gov.uk (The National Archives) (2015). Consumer Rights Act 2015, section 51 (opens in a new tab) ↑

  4. legislation.gov.uk (The National Archives) (2015). Consumer Rights Act 2015, section 49 (opens in a new tab) ↑