Key takeaways
- Most install-day problems start before the day: parts, access, the cancellation period and what the customer expects.
- Flush and inhibit the system and commission to BS 7593 before the new boiler runs[1].
- Fit a carbon monoxide alarm in the room with any new or replacement fixed gas appliance in England[2]; many homes still have none[3].
- Finish the paperwork on site: digital Benchmark record, scheme notification and the information the owner must receive within five days[1][4].
Why a written install-day checklist pays
Every heating firm has engineers who install boilers well. The difference between firms is how consistently they do it when the engineer is tired, the van is short of a fitting or the customer is anxious. A written checklist turns good habits into a standard, makes training easier and gives you evidence when a customer complains months later. It also lets the office see where days overrun, because the same steps are recorded on every job.
The checklist below follows a typical one-day combi or system boiler replacement. Adapt the timings and steps to your own work, but keep the order: preparation, protection, removal, system preparation, installation, commissioning, handover and paperwork.
Before the day
If the contract was agreed in the customer's home or at a distance, such as by phone or email, the customer has a cancellation period that ends 14 days after the contract is made[5]. You must not start within that period unless the customer has expressly asked you to, and for off-premises contracts that request must be on a durable medium such as an email or signed form[6]. Get the request in writing before you book an early start, and keep it with the job.
- Confirm the date, arrival time and how long heating and hot water will be off.
- Check the parts list against the survey, including flue components, filter, controls, valves and any condensate pump.
- Confirm parking, access and where the old boiler and packaging will go.
- Ask the customer to clear the cupboard or area around the boiler and the route to it.
- Tell the customer about any work in other rooms, such as new thermostatic radiator valves.
- Send the engineer the survey photos, flue decision and any notes on vulnerable occupants.
Arrival and protection
- Introduce yourself, confirm the plan and the expected finish time with the customer.
- Lay dust sheets and floor protection along the route and around the work area.
- Photograph the existing installation, the surrounding decoration and any existing damage.
- Check the gas meter, pipework and the existing flue for anything that changes the plan.
- Isolate gas, water and electrics safely and label the isolations.
Take a minute to note anything the customer says about how they use the heating. It feeds into how you set the controls later and shows you were listening, which matters at handover.
Preparing the system
Approved Document L says that before a new heating appliance is installed, central heating and primary hot water circuits should be thoroughly cleaned and flushed, a suitable chemical inhibitor should be added to protect against scale and corrosion, and in hard water areas the feed to water heaters and the hot water circuit of combination boilers should be treated to reduce limescale[1]. Domestic central heating systems should be prepared and commissioned to BS 7593[1].
In practice that means choosing a flushing method suited to the system's condition, fitting a magnetic or other system filter where your boiler manufacturer requires or recommends one, and recording the inhibitor product and the test result. Many warranties depend on it, and a new heat exchanger full of sludge from an old system is a callback waiting to happen.
Installation
- Fit the boiler, flue and condensate to the manufacturer's instructions, using the flue position agreed at survey.
- Check the gas supply is sized for the new appliance from the meter to the boiler, not just at the boiler connection.
- Route the condensate pipe internally where possible and follow the manufacturer's sizing and fall requirements.
- Fit thermostatic room controls in each room where the boiler is being replaced, unless an exception applies[1].
- Check a combi selected for the job can modulate down to the home's typical heating load[1].
If you find something on the day that changes the job, such as an unsafe flue position or a gas supply that needs upgrading, stop and explain it to the customer before carrying on. Agree any extra cost in writing. Surprises on the invoice are the most common source of install complaints.
Occupied homes and vulnerable customers
Most boiler replacements happen in homes where people are living, often in winter and often after a breakdown. A day without heating or hot water is an inconvenience for most households and a real risk for some. Ask at booking whether anyone in the home is elderly, unwell, very young or relies on heating for a medical reason, and plan the day around the answer. The same questions belong in your phone triage for breakdowns.
- Offer a temporary electric heater for the main living room where heating will be off for most of the day.
- Schedule the gas isolation so the customer can make a hot drink first, and tell them when hot water will be back.
- Keep the walkway clear and protected for anyone with mobility needs.
- Explain the controls slowly at handover and leave large-print instructions where needed.
- Note any agreed adjustments on the job sheet so the next engineer knows.
These steps cost very little and are the kind of detail customers mention in reviews.
The carbon monoxide alarm
In England, where a new or replacement fixed gas appliance other than a cooker is installed in a dwelling, Approved Document J says a carbon monoxide alarm should be fitted in the room where the appliance is located[2]. The alarm should meet BS EN 50291-1:2018 and be battery powered for the working life of the alarm with an end-of-life warning, or be a hard-wired mains Type A alarm with a sensor failure warning[2]. Site it on the ceiling at least 300mm from any wall, or high on a wall but not within 150mm of the ceiling, and between 1m and 3m horizontally from the appliance[2].
Source: Ministry of Housing, Communities and Local Government (GOV.UK), 2024[3]
Show the data
| Item | Value |
|---|---|
| 2023 | 60% |
| 2024 | 62% |
Only 62% of homes in England had a carbon monoxide alarm in 2024[3]. Check the rest of the home while you are there, and advise on alarms in other rooms with fuel-burning appliances. Record where you fitted the alarm and its expiry date.
Commissioning
Tightness test and purge
Test the installation pipework, purge it and record the results.
Check operating pressure
Measure working pressure at the appliance with it running at full rate.
Combustion analysis
Check flue integrity and combustion readings against the manufacturer's values.
Set the boiler to the home
Set the heating output and flow temperature to suit the heat loss and emitters rather than leaving factory defaults.
Commission controls
Set the programmer, room thermostat and any smart or weather compensation controls, and check each zone switches correctly.
Balance and check
Balance the radiators, check for leaks and confirm the condensate drains.
Complete the record
Fill in the digital Benchmark record, now online or in the Benchmark apps rather than on paper[4].
Example: a one-day combi swap timeline
| Time (Example) | Task |
|---|---|
| 08:00 | Arrive, walkthrough, protection, photos |
| 08:30 | Isolate, drain down, remove old boiler |
| 10:00 | Flush system, fit filter |
| 11:30 | Fit new boiler, flue and condensate |
| 13:30 | Gas and water connections, controls wiring |
| 15:00 | Fill, inhibit, tightness test, commission |
| 16:30 | CO alarm, balance, clean up |
| 17:00 | Handover and paperwork |
Example (fictional): on one job the flushing took two hours longer than planned because the old system was heavily sludged. Because the engineer had recorded each stage, the office could see where the day went, phoned the next morning's customer early to move their start, and added a sludge check to the survey sheet so later quotes allowed more time.
Clean up, handover and paperwork
Leave the area as you found it, remove the old boiler and packaging, and check the photos you took on arrival against the finished room. Then hand over properly: show the customer the controls, the pressure gauge, the filter and the alarm, and agree the first service date.
Building regulations require the person carrying out the work to give the owner, within five days of completion, enough information about the heating system and its maintenance for it to be run efficiently[1], and Approved Document L says operating and maintenance instructions should be easy to understand, specific to the dwelling and durable[1]. Notify the work through your competent person scheme so the owner receives a compliance certificate without needing separate building regulations approval[7].
End every install with three things done on site: the digital Benchmark record, the scheme notification started and the customer's first service booked.
Frequently asked questions
Can I start a boiler install within 14 days of the customer agreeing?
Only if the customer has expressly asked you to start early, and for contracts agreed off premises that request must be on a durable medium such as email.
Do I have to fit a CO alarm with a new boiler?
In England, Approved Document J says an alarm should be provided in the room where a new or replacement fixed gas appliance, other than a cooker, is installed.
Is power flushing required?
Approved Document L requires the system to be thoroughly cleaned and flushed and commissioned to BS 7593. Choose the method that suits the system's condition.
Is the Benchmark checklist still on paper?
No. The paper version is no longer maintained and the record has moved online and to the Benchmark apps.
References
GOV.UK (Ministry of Housing, Communities and Local Government) (2023). Approved Document L, Volume 1: Dwellings (2021 edition incorporating 2023 amendments) (opens in a new tab) ↑
GOV.UK (Ministry of Housing, Communities and Local Government) (2022). Approved Document J: Combustion appliances and fuel storage systems (2010 edition incorporating 2010, 2013 and 2022 amendments) (opens in a new tab) ↑
Ministry of Housing, Communities and Local Government (GOV.UK) (2024). English Housing Survey 2024 to 2025: Chapter 1, housing quality (opens in a new tab) ↑
Heating and Hotwater Industry Council (HHIC) (2026). Benchmark goes digital - what homeowners need to know (opens in a new tab) ↑
legislation.gov.uk (The National Archives) (2013). The Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013, regulation 30 (opens in a new tab) ↑
legislation.gov.uk (The National Archives) (2013). The Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013, regulation 36 (opens in a new tab) ↑
GOV.UK (2026). Building regulations approval (opens in a new tab) ↑