BS 7593 water treatment: what installers must do

What BS 7593 and Approved Document L expect on heating water treatment: cleaning, inhibitor dosing and testing, filters, scale and the record to leave.

Ava research teamPublished 7 min read

On this page
  1. What BS 7593 is and why it now matters more
  2. The four parts of good water treatment
  3. Cleaning to a standard you can show
  4. Inhibitor: dose, test and label
  5. Filters and scale protection
  6. Lower flow temperatures and microbial growth
  7. Maintenance: the part most often skipped
  8. Reading what the water tells you at a service
  9. Worked Example: a commissioning record that tells the story
  10. Records, warranties and your position
  11. Frequently asked questions
  12. References

Key takeaways

  • Approved Document L expects domestic central heating systems to be prepared and commissioned to BS 7593, the 2019 code of practice on preparing, commissioning and maintaining heating water[1].
  • The same expectation carries into the 2026 edition, alongside cleaning, inhibitor and hard water treatment[2].
  • Water treatment is not a one-off: the code covers maintenance, so inhibitor levels and water quality belong in every annual service.
  • The commissioning record is how you prove it was done; Benchmark is a recognised way to show Part L commissioning[3].

What BS 7593 is and why it now matters more

BS 7593:2019 is the British Standard code of practice for the preparation, commissioning and maintenance of domestic central heating and cooling water systems[1]. For years many installers treated it as background reading. Approved Document L changed that by saying, in its commissioning section, that domestic central heating systems should be prepared and commissioned to BS 7593[1]. The 2026 edition keeps the same wording[2].

The reason is the equipment you now fit. In 2001 only 3% of English homes had a condensing boiler of any kind; by 2024 the figure was 82%, with 63% on condensing combis[4]. Condensing heat exchangers have narrow waterways and lighter materials than the cast iron boilers they replaced, and they are far less tolerant of sludge, scale and corrosion.

Homes in England with condensing boilers, 2001 and 2024English Housing Survey
Homes in England with condensing boilers, 2001 and 2024Column chart. Condensing combination boiler: 2001 2%, 2024 63%; Other condensing boiler: 2001 1%, 2024 19%.0%20%40%60%80%Condensing combination boiler · 2001: 2%2%Condensing combination boiler · 2024: 63%63%Condensing combination boilerOther condensing boiler · 2001: 1%1%Other condensing boiler · 2024: 19%19%Other condensing boilerHomes in England with condensing boilers, 2001 and 2024Column chart. Condensing combination boiler: 2001 2%, 2024 63%; Other condensing boiler: 2001 1%, 2024 19%.Condensing combination boilerCondensing combination boiler · 2001: 2%2%Condensing combination boiler · 2024: 63%63%Other condensing boilerOther condensing boiler · 2001: 1%1%Other condensing boiler · 2024: 19%19%
  • 2001
  • 2024

Source: Ministry of Housing, Communities and Local Government (GOV.UK), 2024[4]

Show the data
Item20012024
Condensing combination boiler2%63%
Other condensing boiler1%19%

This is a summary for installers, not a substitute for the standard. Buy or access a copy of BS 7593:2019 and read it alongside the boiler and chemical manufacturers' instructions.

The four parts of good water treatment

  1. Clean: remove installation debris on new systems and sludge, corrosion products and old chemicals on existing ones before the new appliance is connected.
  2. Protect: dose a suitable inhibitor at the concentration the manufacturer specifies for the system volume, and confirm it with a test.
  3. Filter: fit an in-line system filter to catch magnetite and debris that cleaning cannot fully remove and corrosion that continues afterwards.
  4. Maintain: check inhibitor concentration and water condition at each service, top up or re-treat as needed, and clean the filter.

Approved Document L puts the first two in plain words: thoroughly clean and flush all central heating and primary hot water circuits before a new appliance is installed, and add a suitable chemical inhibitor to protect against scale and corrosion[1]. In hard water areas it adds treatment of the feed to water heaters and combi hot water circuits[1].

Cleaning to a standard you can show

The cleaning method is yours to choose, but the outcome must be demonstrable. A useful discipline is to take water samples before and after, from the same drain point, and photograph them. Where you carry a meter, compare the total dissolved solids or conductivity of the system water with the incoming mains after rinsing: a figure close to the mains suggests the cleaner and loosened debris have been flushed out.

  • New systems: flush out flux, jointing compound and swarf, ideally with a cleaner suitable for new installations.
  • Existing systems: choose chemical, mains or powerflush cleaning based on contamination and system condition.
  • Always rinse: residual cleaner can attack components and distort inhibitor test results.
  • Note any radiators replaced instead of cleaned and why.

Inhibitor: dose, test and label

Inhibitor is only effective at the right concentration. Under-dosing is common because system volume is guessed. Estimate the volume from the boiler, pipework and radiator types, dose to the chemical maker's instructions and then test, rather than assuming one bottle is enough for any house.

  1. Estimate the volume

    Add boiler water content, radiator volumes from their type and size, and an allowance for pipework.

  2. Dose through a suitable point

    Use a radiator, a dosing pot or the filter, as the product instructions allow, and circulate the system.

  3. Test the concentration

    Use the manufacturer's test kit or a lab test service and record the result.

  4. Label the system

    Fix a label near the boiler showing the inhibitor product, date and concentration so the next engineer can match it.

  5. Record it

    Write the product, quantity and test result on the commissioning record.

Filters and scale protection

An in-line filter on the return to the boiler is now standard practice and is often a condition of extended manufacturer warranties. Choose one sized for the pipework, fitted where it can be isolated, opened and cleaned at service without draining the system. Record its make and model.

  • Fit the filter where an engineer can reach it with the boiler cover on and a towel underneath, not behind a kitchen unit that has to be removed.
  • Fit isolating valves either side so it can be opened without draining down.
  • Check the filter's flow direction arrow before you finish the joints.
  • Show the customer where it is, so they understand why the service includes cleaning it.

Hard water is a separate issue from heating circuit water. Approved Document L defines hard water as more than 200ppm of calcium carbonate and expects the feed to water heaters and combi hot water circuits to be treated in such areas[1]. Handle it alongside, not instead of, the heating circuit treatment.

Lower flow temperatures and microbial growth

Systems designed to run at lower flow temperatures, which Part L now encourages, can be more prone to microbial growth than systems running hot. BS 7593 deals with when a biocide should be considered. If you are commissioning a low-temperature system, underfloor heating or a heat pump circuit, read that part of the code and the chemical maker's guidance, and record whether a biocide was used and why.

Signs of microbial problems include slimy deposits, a smell when venting radiators, and poor heat transfer in underfloor loops. They are far easier to prevent than to clear.

Maintenance: the part most often skipped

BS 7593 covers maintenance as well as commissioning, which means water treatment belongs in the annual service. A service that checks the boiler but ignores the water misses one of the commonest causes of failure.

  • Test inhibitor concentration and top up if low; if the water is badly discoloured, recommend cleaning rather than just adding more inhibitor.
  • Open and clean the filter, and note how much debris it held compared with last time.
  • Check system pressure history; frequent top-ups dilute inhibitor and bring in oxygen.
  • Record results on the service record so the trend is visible.

Reading what the water tells you at a service

Water condition at a service is a quick health check on the whole system, and it is often the first sign of a problem that will become a breakdown. Train every engineer to draw a sample and to record what they see in the same terms, so trends are visible across visits.

Interpreting a heating water sample at service
What you seeLikely causeWhat to do
Clear water, inhibitor in rangeSystem healthyRecord and move on
Clear water, inhibitor lowDilution from top-ups or a leakFind why it was topped up, then re-dose
Black or grey waterMagnetite from ongoing corrosionTest inhibitor, clean filter, recommend cleaning if heavy
Orange or brown waterAir entering the systemLook for pumping over, a leak or a faulty auto air vent
Slime or smellMicrobial growthConsider cleaning and biocide treatment as the code advises

The pattern matters more than a single reading. A filter that held a spoonful of debris last year and a handful this year is telling you corrosion has restarted, which usually means oxygen is getting in. Fixing the cause is worth far more than another bottle of inhibitor.

Explain the result to the customer in one sentence and write it on the service record. 'Your heating water is clean and protected' is reassuring. 'Your water is darker than last year and I think air is getting in; here is what I recommend' gives them a reason to act before the boiler suffers.

Worked Example: a commissioning record that tells the story

Example: water treatment entries for a fictional combi replacement
ItemEntry on the record
CleaningChemical clean with named cleaner, mains rinse; before and after photos attached
Rinse checkSystem water close to mains reading after rinse
InhibitorNamed product, two bottles for an estimated system volume; test result within range
FilterNamed magnetic filter on boiler return, isolating valves fitted
ScaleHardness checked by supplier lookup; scale reducer fitted on combi cold inlet
LabelInhibitor label fixed next to boiler with date

Example. With these entries, a warranty assessor two years later can see what was done without phoning anyone. The next engineer can test the inhibitor and compare with the commissioning figure, and the customer can see that the protection they paid for was actually fitted.

Records, warranties and your position

Benchmark describes completing its checklist as a means of meeting the Part L commissioning requirements[3], and the record is now held online and in apps rather than in a paper booklet[5]. Use it to log water treatment in detail, because manufacturers' warranty terms usually echo BS 7593.

There is also the implied term that services are carried out with reasonable care and skill[6]. If a heat exchanger blocks in the first year, evidence that you cleaned, dosed, tested and filtered to the code of practice is your best defence. See flushing method options and magnetic filters for the practical detail.

Frequently asked questions

Is BS 7593 mandatory?

It is a code of practice, but Approved Document L says domestic central heating systems should be prepared and commissioned to BS 7593, and manufacturers' warranty terms usually follow it. In practice, treat it as the expected standard.

How often should inhibitor be checked?

Check it at each annual service and after any work that drains or dilutes the system, and record the result.

Do I need a filter to comply?

A system filter is widely recommended and often a warranty condition. Check the current code and the boiler maker's instructions for the specific requirement.

What should I leave for the customer?

A completed commissioning record with cleaning method, inhibitor product and test result, filter details and scale protection, plus a label near the boiler.

References

  1. Ministry of Housing, Communities and Local Government (GOV.UK) (2023). Approved Document L, Volume 1: Dwellings (2021 edition incorporating 2023 amendments) (opens in a new tab) ↑

  2. Ministry of Housing, Communities and Local Government (GOV.UK) (2026). Approved Document L, Volume 1: Dwellings (2026 edition) (opens in a new tab) ↑

  3. The Benchmark Scheme (2026). Benchmark: quality in domestic heating and hot water (opens in a new tab) ↑

  4. Ministry of Housing, Communities and Local Government (GOV.UK) (2024). English Housing Survey 2024 to 2025: Chapter 2, energy efficiency (opens in a new tab) ↑

  5. Heating and Hotwater Industry Council (HHIC) (2026). Benchmark goes digital - what homeowners need to know (opens in a new tab) ↑

  6. legislation.gov.uk (The National Archives) (2015). Consumer Rights Act 2015, section 49 (opens in a new tab) ↑

Book a demo

See Ava handle your calls.

Book a short demo. We’ll walk through your calls and workflow, and agree what Ava should take care of.

Book a demo