Key takeaways
- Material prices for repair and maintenance work rose 6.2% in the year to September 2026[1]; a quote accepted months after it was written can lose its margin.
- Give every material-heavy quote an end date, written as a date rather than a number of days.
- For domestic customers, requote after expiry rather than relying on a clause that lets you raise the price; any change needs their express agreement[2].
- Ask merchants for price holds on large items, and order on acceptance with a deposit.
- Watch the trend: the repair and maintenance materials index stood at 168.7 in September 2026, against 117.1 in January 2021[3].
Why quotes go stale
A quote is a promise made at today's prices. Customers do not always accept straight away: a bathroom quote might sit on the fridge for two months while they save, and a boiler quote given in summer might be accepted in the first cold week of November. If material prices rise in between, the margin you built into the quote shrinks or disappears, and you do the job for less than it cost you.
The answer is not to pad every quote against every possible price rise. It is a small set of tools: a clear validity date, a sensible approach to requoting, price holds from your merchant, and deposits that let you buy materials as soon as the customer says yes.
How fast material prices move
The government's construction material price index for repair and maintenance work shows how much prices have moved in recent years. After a sharp rise in 2021 and 2022, prices eased slightly, then climbed again; by September 2026 the index stood at 168.7, with 2015 as 100[3].
Source: Department for Business and Trade (GOV.UK), 2026[3]
Show the data
| Period | Value |
|---|---|
| Jan 2021 | 117.1 index (2015=100) |
| Jul 2021 | 129.3 index (2015=100) |
| Jan 2022 | 143.5 index (2015=100) |
| Jul 2022 | 159.2 index (2015=100) |
| Jan 2023 | 151.6 index (2015=100) |
| Jul 2023 | 153.2 index (2015=100) |
| Jan 2024 | 150.6 index (2015=100) |
| Jul 2024 | 154 index (2015=100) |
| Jan 2025 | 153.3 index (2015=100) |
| Jul 2025 | 158.7 index (2015=100) |
| Jan 2026 | 158.6 index (2015=100) |
| Sep 2026 | 168.7 index (2015=100) |
The latest year has been another steep one. The index for repair and maintenance work rose 6.2% in the year to September 2026, and the index for all construction work rose 7.2%, up from 6.4% in the year to August[1]. Some plumbing lines moved much faster: rigid pipes and fittings rose 16.9% over the same twelve months[1]. Energy costs feed through into material prices as well, and 69% of UK businesses expressed some concern about energy prices in late October 2026[4].
Five ways to protect a quote
No single tool covers every job. Small repairs need little more than a validity date, while a bathroom booked three months ahead may need a date, a deposit and a merchant price hold together. Use the table to pick the combination that fits the size of the job and the share of the price that is materials.
| Tool | How it works | Best for |
|---|---|---|
| Validity date | The price stands until a stated date; after that, you requote | Every quote, especially those with a large materials share |
| Requote on expiry | When a customer accepts after the date, you check current prices and confirm or revise the figure before booking | Domestic customers |
| Merchant price hold | Your merchant holds a price on named items for a period | Boilers, cylinders, radiators and other big-ticket items |
| Deposit and early ordering | A deposit on acceptance pays for materials bought straight away | Installs and bathrooms booked weeks ahead |
| Fluctuation clause | The contract allows the price of named materials to change in line with a stated measure | Larger commercial and subcontract work |
Setting the validity date
- Write a date, not a period: 'This quote is valid until 6 December 2026' is clearer than '30 days'.
- Match the length to the materials share. Labour-heavy repairs can stand longer than a quote where most of the price is a boiler or a bathroom suite.
- Shorten the window when prices are moving fast, and say why if customers ask.
- Separate validity from start date: a customer can accept within the window and book a start date later, but you need to say whether the price holds to that start date.
- State what happens after expiry: 'If you would like to go ahead after this date, we will check current prices and confirm the price before booking.'
Requote rather than rely on a clause
For domestic customers, a clean requote after expiry is usually better than a clause that lets you increase the price later. What you tell a consumer about the price can become a term of the contract, and a change to the price information you gave is not effective unless the customer expressly agrees it[2]. A requote keeps that agreement explicit: the customer sees the new figure, and decides.
Fluctuation clauses are more common in business-to-business work, such as subcontract jobs for builders, where the contract may tie named materials to a published index. If you use one, name the materials, the measure and the dates, and explain it before the contract is agreed. Take advice before using such a clause with consumers.
Merchant price holds and ordering early
- Ask your main merchant whether they will hold a price on named big-ticket items for a set period once you have a customer's acceptance.
- Order boilers, cylinders and sanitaryware as soon as the deposit clears, and store or schedule delivery for the start date.
- Keep the merchant quote reference with the job, so the price you were offered is on record.
- Check delivery lead times when quoting; a part that is cheap but six weeks away can cost you the job.
- Review your price file every month for the items you quote most often, not only when an invoice surprises you.
Keep your price file current
Most quoting errors come from an out-of-date price file rather than from sudden price rises. If your quoting software or spreadsheet holds standard prices for common items, set a monthly date to update the twenty or thirty items you quote most often: boilers you fit regularly, cylinders, radiators in common sizes, valves, filters, controls and pipe. Note the date of the last update at the top of the file, so anyone quoting can see whether it is current.
Check the published material price figures when they come out each month, too. They will not tell you what your merchant will charge, but a sharp rise in a category you use heavily is a prompt to recheck your own prices before the next batch of quotes.
Deposits that pay for materials
A deposit on acceptance lets you buy the main materials at the quoted price straight away, which removes most of the risk for jobs booked weeks ahead. Set the deposit to cover the main items, say so in the payment terms on the quote, and explain on the acceptance call what it pays for. Customers are generally comfortable with a deposit when they know it is buying their boiler or bathroom suite, not sitting in your account. For more on payment terms, see what to include in a plumbing quote.
Wording for the quote and the requote
- On the quote: 'Prices are based on current material costs and are valid until 6 December 2026. Materials are ordered when we receive your deposit, and the price is then fixed for the agreed start date.'
- On an expired quote, by email: 'Thanks for coming back to us. As your quote has passed its validity date, we've checked current prices. The boiler and cylinder have gone up since we quoted, so the new total is shown below. Everything else is unchanged.'
- On the phone: 'Some of the materials have gone up since we quoted. I've rechecked everything and the new figure is this. If you're happy with that, I can book you in.'
Talking about price rises without losing the job
Customers accept a revised price far more readily when it is explained early, specifically and without apology for things outside your control. Point to the items that changed, not a vague 'costs have gone up'. Offer a choice where there genuinely is one, such as an alternative model at the original price. And never revise a price after the work has started without stopping and agreeing it first; that turns a reasonable conversation into a dispute.
When a customer accepts an expired quote
Thank them and check the date
Confirm whether the quote is inside or outside its validity date before giving any start date.
Recheck the main items
Price the big-ticket materials again from your merchant. Labour rates may also have changed if you reviewed them since.
Decide whether to hold or revise
If the change is small, you may choose to honour the old price for goodwill; if not, revise it.
Send the revised figure in writing
Show what changed and why, and ask the customer to confirm acceptance of the new price.
Take the deposit and order
Once the customer agrees, take the deposit and order the main materials straight away.
Example: a summer quote accepted in winter
Example: a fictional firm in Ipswich quotes a system boiler and cylinder replacement in June, valid until the end of July. The customer calls in October to accept. The office rechecks prices and finds the cylinder and several pipe fittings have gone up noticeably, while the boiler is almost unchanged. It sends a revised quote with the changed lines highlighted and a note explaining the validity date. The customer accepts, pays the deposit the same week, and the firm orders everything at once. Had it honoured the June price, the job would have made about half its planned margin.
Frequently asked questions
How long should a plumbing quote be valid for?
It depends on how much of the price is materials and how fast prices are moving. Many firms use about a month for material-heavy quotes and longer for labour-heavy work. Always write an end date on the quote.
Can I increase my price after the customer accepts?
Not without their express agreement; a change to the price information you gave is not effective unless agreed[2]. Protect yourself with a validity date, a requote after expiry, and a deposit that lets you buy materials straight away.
How much have plumbing material prices gone up?
The construction material price index for repair and maintenance work rose 6.2% in the year to September 2026, and rigid pipes and fittings rose 16.9%[1].
References
Department for Business and Trade (GOV.UK) (2026). Building materials and components statistics: October 2026 (commentary) (opens in a new tab) ↑
legislation.gov.uk (The National Archives) (2015). Consumer Rights Act 2015, section 50 (opens in a new tab) ↑
Department for Business and Trade (GOV.UK) (2026). Building materials and components statistics: October 2026, Table 1a (monthly construction material price indices) (opens in a new tab) ↑
Office for National Statistics (2026). Business insights and impact on the UK economy: latest bulletin (opens in a new tab) ↑